Millers Branch Solar I
200 MW generation in Haskell, TX · In queue since December 2019 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Phase
Signed Jun 2021
Queue → IA
1y 6m
IA → COD
4y 6m
Total Duration
1y 6m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-30
- 2023-09·EDF Renewables→Southern Powersource
Southern Power acquired 200 MW Millers Branch project from EDF Renewables with expansion potential to 500 MW
sourceMillers Branch Solar I is a proposed 200 MW solar generation project located in Haskell County, Texas. The developer is Miller's Branch Solar, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-22INR0270, with a queue entry date of December 17, 2019, and a proposed commercial operation date of December 1, 2025. The project's Interconnection Agreement (IA) was executed on June 14, 2021.
The Millers Branch Solar I project has been featured in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Miller's Branch Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Gauss Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-19
View all articlesNo Ask reports yet for this entity.
Ask about Millers Branch Solar IForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.