Millers Branch Solar I (ERCOT-22INR0270) — Project Summary

Queue ID
ERCOT-22INR0270
Capacity
200 MW
Technology
Solar
Status
active
Location
Haskell, TX
Region
ERCOT
Developer
Miller's Branch Solar, LLC
IA Status
IA Executed

Millers Branch Solar I

ERCOT-22INR0270BetaActiveSolarERCOTLBNL

200 MW generation in Haskell, TX · In queue since December 2019 · Proposed COD December 2025

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200 MW

Capacity

1

Components

Solar

6y 11m

In Queue

IA Executed

IA Phase

Signed Jun 2021

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 6m

IA → COD

4y 6m

Total Duration

1y 6m

Schedule

11 months past proposed COD

Construction75%
Queue EntryDec 17, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 14, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-12-30

Queue history
22INR0270 · 67 monthly ERCOT reports, Jun 2020 – Dec 2025

Projected COD moved

5 times

Jun 2022 → Dec 2025

Net change

+42 months

first report to latest

Capacity

513 → 200 MW

changed in the reports

Latest stage

Commercial operation

last listed Dec 2025

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 17, 2019
Facilities study approvedNov 1, 2024
Interconnection agreement signedJun 14, 2021
Approved for energizationAug 18, 2025
Approved for synchronizationAug 25, 2025
Approved for commercial operationJan 27, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 2y 6m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestonecapacity expansion announcedPV Tech · 2024-05-02
Expected CODQ2 2026PV Tech · 2024-05-02

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jun 2026
Differs from queue: Dec 30, 2025
Developer in saved assessment
Southern Power
Filed as Miller's Branch Solar, LLC
Status at research time
Active
Active — under construction with phased expansion to 512 MW total capacity, Q2 2026 COD target
Financing
Secured
Financing secured through Southern Power acquisition and subsequent expansion announcements; specific financing amounts not publicly disclosed but project is fully funded and under construction
Ownership history
  1. 2023-09·EDF Renewables→Southern Powerrechargenews.com

Milestones in this assessment

IA executedJun 14, 2021

Interconnection Agreement executed with ERCOT

pv-tech.org
Ownership changeSep 2023

Southern Power acquired 200 MW Millers Branch project from EDF Renewables with expansion potential to 500 MW

rechargenews.com
GroundbreakingMay 2024

Construction phase with 180 MW capacity expansion announced

pv-tech.org
Financing closeNov 2024

Further expansion announced bringing total capacity to 512 MW

prnewswire.com
COD targetJun 2026Latest in this assessment

Expected commercial operation Q2 2026 for expanded facility

pv-tech.org
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. pv-tech.org/southern-power-180mw-capacity-millers-branch-solar-farm-texas/
  2. rechargenews.com/wind/southern-power-advances-texas-solar-ambitions-with-up-to-500mw-project-swoop/2-1-1522600
  3. prnewswire.com/news-releases/southern-power-announces-further-expansion-of-millers-branch-solar-facility-in-texas-302312607.html
  4. renewablesnow.com/news/southern-power-upsizes-texas-pv-project-to-512-mw-with-new-phase-875056/
  5. csrwire.com/press-release/southern-power-expands-millers-branch-solar-facility-texas/

Commercial operation date: LBNL proposed COD of Dec 2025 is stale. Multiple 2024 sources (PV Tech May 2024, PR Newswire Nov 2024, Renewables Now Nov 2024) consistently cite Q2 2026 as the target COD for the expanded facility.

Developer: LBNL filing entity 'Miller's Branch Solar, LLC' is a project SPV. Southern Power (subsidiary of Southern Company) is the actual operating company that acquired the project from EDF Renewables in Sept 2023 and has announced multiple expansions.

Status: LBNL status 'Active' with IA Executed (June 2021) is accurate. Project is currently under construction per May 2024 PV Tech article, with Southern Power announcing multiple capacity expansions (180 MW in May 2024, additional phase in Nov 2024 bringing total to 512 MW).

Project lifecycle
as of 2024-05-02
PhaseConstructionPV Tech · 2024-05-02
OperationalNoPV Tech · 2024-05-02
TechnologySolarPV Tech · 2024-05-02
DeveloperSouthern PowerPV Tech · 2024-05-02
PPA offtakerNet Zero Consortium for Buyers (Bio-Rad Laboratories, Cadence Design Systems, Cisco, IDEXX Laboratories, Juniper Networks, PTC)PV Tech · 2024-05-02

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Millers Branch Solar I is a proposed 200 MW solar generation project located in Haskell County, Texas. The developer is Miller's Branch Solar, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-22INR0270, with a queue entry date of December 17, 2019, and a proposed commercial operation date of December 1, 2025. The project's Interconnection Agreement (IA) was executed on June 14, 2021.

The Millers Branch Solar I project has been featured in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Dec 2025.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Haskell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Miller's Branch Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)

Data Source

LBNL

DeveloperSouthern Power±PV Tech · 2024-05-02
TransactionAcquisitionRenewables Now · 2023-09-22
OfftakerSouthern PowerRenewables Now · 2023-09-22
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Gauss Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-04-19