Felix North Solar
200.98 MW hybrid in Wilbarger, TX · In queue since January 2019 · Proposed COD December 2028
200.98 MW
Capacity
1
Components
Solar
7y 10m
In Queue
IA Executed
IA Phase
Signed Feb 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
6y 1m
IA → COD
3y 10m
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-31
Projected COD moved
4 times
Dec 2022 → Dec 2028
Net change
+72 months
first report to latest
Capacity
250 → 201 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement date added to ERCOT queue
interconnectionfyi.substack.comERCOT operational planning lists 100.54 MW solar component with 2027 target
ercot.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- ercot.com/files/docs/2025/04/04/Capacity-Changes-by-Fuel-Type-Charts_March_2025.xlsx
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
- ercot.com/files/docs/2025/12/05/MORA_February2026.pdf
- eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
Commercial operation date: ERCOT's March 2025 Capacity Changes report lists Felix North Solar with a 2027 COD target (100.54 MW solar component), while LBNL queue shows 2028-12-31. The ERCOT operational planning document is more current than the queue filing.
Developer: All sources consistently identify Crescent Solar, LLC as the developer. No parent company or shell-LLC distinction found in available sources.
Status: LBNL shows 'active' status with IA executed 2025-02-21. Interconnection.fyi confirms IA date added February 20, 2025. ERCOT planning documents include project in 2027 capacity forecasts.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Felix North Solar project is a proposed 100.54 MW solar generation facility in Wilbarger County, Texas. Developed by Crescent Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0209, with a queue entry date of January 17, 2019. Its proposed commercial operation date is December 31, 2028, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 100.54 MW of solar photovoltaic generation. It is planned to connect to the grid at the 6101 Riley 345kV point of interconnection. The Felix North Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Crescent Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6101 Riley 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ELECTRAW_1_2
- POI Substation
- Riley Substation