Felix North Solar (ERCOT-22INR0209) — Project Summary

Queue ID
ERCOT-22INR0209
Capacity
200.98 MW
Technology
Solar+Battery
Status
active
Location
Wilbarger, TX
Region
ERCOT
Developer
Crescent Solar, LLC
IA Status
IA Executed

Felix North Solar

ERCOT-22INR0209BetaActiveSolarBatteryERCOTLBNL + Live

200.98 MW hybrid in Wilbarger, TX · In queue since January 2019 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200.98 MW

Capacity

1

Components

Solar

7y 10m

In Queue

IA Executed

IA Phase

Signed Feb 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

6y 1m

IA → COD

3y 10m

Total Duration

6y 1m

Construction75%
Queue EntryJan 17, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 21, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-12-31

Queue history
22INR0209 · 84 monthly ERCOT reports, Sep 2019 – Sep 2026

Projected COD moved

4 times

Dec 2022 → Dec 2028

Net change

+72 months

first report to latest

Capacity

250 → 201 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 17, 2019
Interconnection agreement signedFeb 21, 2025
On ERCOT's inactive listFeb 2023 – Feb 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activityearnings_reportStock Titan · 2026-03-09

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2027
Differs from queue: Dec 31, 2028
Developer in saved assessment
Crescent Solar, LLC
From queue filing
Status at research time
Active
Active — IA executed February 2025, targeting 2027 COD per ERCOT operational planning
Financing
Not recorded

Milestones in this assessment

IA executedFeb 20, 2025

Interconnection Agreement date added to ERCOT queue

interconnectionfyi.substack.com
COD target2027Latest in this assessment

ERCOT operational planning lists 100.54 MW solar component with 2027 target

ercot.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. ercot.com/files/docs/2025/04/04/Capacity-Changes-by-Fuel-Type-Charts_March_2025.xlsx
  2. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
  3. ercot.com/files/docs/2025/12/05/MORA_February2026.pdf
  4. eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx

Commercial operation date: ERCOT's March 2025 Capacity Changes report lists Felix North Solar with a 2027 COD target (100.54 MW solar component), while LBNL queue shows 2028-12-31. The ERCOT operational planning document is more current than the queue filing.

Developer: All sources consistently identify Crescent Solar, LLC as the developer. No parent company or shell-LLC distinction found in available sources.

Status: LBNL shows 'active' status with IA executed 2025-02-21. Interconnection.fyi confirms IA date added February 20, 2025. ERCOT planning documents include project in 2027 capacity forecasts.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Felix North Solar project is a proposed 100.54 MW solar generation facility in Wilbarger County, Texas. Developed by Crescent Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0209, with a queue entry date of January 17, 2019. Its proposed commercial operation date is December 31, 2028, and its interconnection agreement status is currently in the Facility Study phase.

The proposed project consists of 100.54 MW of solar photovoltaic generation. It is planned to connect to the grid at the 6101 Riley 345kV point of interconnection. The Felix North Solar project has appeared in recent news coverage regarding renewable energy development in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Wilbarger

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Crescent Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

6101 Riley 345kV

Data Source

LBNL + Live

CompanyAESStock Titan · 2026-03-09
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
ELECTRAW_1_2
POI Substation
Riley Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.