Delilah Solar 2
317.58 MW generation in Lamar, TX · In queue since November 2018 · Proposed COD December 2026
317.58 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Phase
Signed Dec 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 1m
IA → COD
6 years
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-31
Projected COD moved
12 times
Dec 2022 → Dec 2026
Net change
+48 months
first report to latest
Capacity
400 → 318 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2024-04·Delilah Solar Energy II LLC→WEC Energy Groupbizjournals.com
Milestones in this assessment
WEC Energy Group reported to invest $459M in acquiring a solar project, linked to Delilah Solar 2.
bizjournals.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- bizjournals.com/milwaukee/news/2024/04/29/wec-energy-invests-459-million-in-solar-project.html
- ercotqueue.com/project/22INR0203
- ercot.com/files/docs/2025/09/02/Stand-Alone-Generation-Resources-as-of-09.01.25-v2.pdf
- infrasure.ai/project/ercot-22inr0203-delilah-solar-2
Commercial operation date: ercotqueue.com lists the project as 'Currently Commissioned', and ERCOT's 09.01.25 Stand-Alone Generation Resources list includes DELILAH SOLAR 2 (DELILA_2_G1, 107 MW). Together these suggest it was operating by about 2025, ahead of LBNL's 2026-12-31. Infrasure shows a May 2026 proposed COD, which also points earlier than LBNL. No source gives an exact COD date.
Developer: The news extraction (Business Journals, 2024-04-29) reports WEC Energy Group as buyer in a $459M solar acquisition linked to this project, while LBNL and ERCOT sources still show the Delilah Solar Energy II LLC shell. The article's text was not available to confirm the project name, and the original developer is not identified in the sources (the Invenergy/Verizon article does not name Delilah).
Status: ERCOT's own resource registry (Sept 2025) and ercotqueue's 'Commissioned' status indicate the project has moved past the queue stage. Other aggregators (Cleanview, Groundtrace) still call it planned or under construction, but those entries are undated and likely lag.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Delilah Solar 2 is a proposed solar generation project located in Lamar County, Texas, with a total capacity of 317.58 MW. The developer is Delilah Solar Energy II LLC. The project is in the ERCOT interconnection queue as entry ERCOT-22INR0203, with a queue entry date of November 20, 2018, and a proposed commercial operation date of May 30, 2026. The interconnection agreement (IA) has been executed as of December 22, 2020.
The Delilah Solar 2 project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Delilah Solar Energy II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV TTRSW 11688
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.