Maleza Storage (ERCOT-21INR0456) — Project Summary

Queue ID
ERCOT-21INR0456
Capacity
150.83 MW
Technology
Solar+Battery
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
Brush Storage, LLC
IA Status
Facility Study

Maleza Storage

ERCOT-21INR0456BetaActiveBatteryBatteryERCOTLBNL + Live

150.83 MW generation in Wharton, TX · In queue since October 2019 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

150.83 MW

Capacity

1

Components

Battery

7y 1m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

9y 2m

Facilities Study50%
Queue EntryOct 31, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Queue history
21INR0456 · 74 monthly ERCOT reports, Aug 2020 – Sep 2026

Projected COD moved

14 times

Dec 2021 → Dec 2028

Net change

+84 months

first report to latest

Capacity

150 → 151 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 31, 2019

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2028
From queue filing
Developer in saved assessment
Sunchase Power
Ownership change in saved research
Status at research time
Active
Active — Facility Study phase, no IA executed. Sister project Maleza Storage II (256 MW) signed IA in April 2026, suggesting original Maleza Storage may advance similarly.
Financing
Not recorded
Ownership history
  1. 2022-08·Borrego→ECP (energy transition investor)energy-storage.news
  2. —·Brush Storage, LLC (original filing entity)→Sunchase Power (current operator)cleanview.co

Milestones in this assessment

Ownership changeAug 2022

Borrego completed sale of development business (including storage projects) to ECP

energy-storage.news
IA executedApr 2026Latest in this assessment

Sister project Maleza Storage II (256 MW) signed ERCOT interconnection agreement under Sunchase Power

cleanview.co
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. energy-storage.news/borrego-completes-sale-of-solar-pv-energy-storage-development-arm/
  2. interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&ItemMatch=Equal&FilingParty=centerpoint&DocumentType=ALL&SortBy=FilingParty&SortOrder=Descending
  3. cleanview.co/news/battery/sunchase-power-signs-interconnection-agreement-for-256-1-mw-maleza-storage-ii-20260401
  4. cleanview.co/power-projects/planned/battery-storage-projects/texas/21INR0456/maleza-storage

Commercial operation date: LBNL proposes 2028-12-31 COD. No independent news sources provide alternative COD targets. Project remains in Facility Study phase with no IA executed, making 2028 target plausible but unconfirmed by external sources.

Developer: LBNL filing entity is 'Brush Storage, LLC' (project shell). April 2026 Cleanview article states 'Sunchase Power Signs IA for 256 MW Maleza Storage II' indicating Sunchase Power is the current operating developer. Borrego sold its development business to ECP in August 2022, and Brush Storage LLC appears to be the legal vehicle for these projects now under Sunchase Power's portfolio.

Status: LBNL status is 'active' with IA status 'Facility Study'. Texas PUC filings from May 2026 show ongoing interconnection agreement amendments with CenterPoint Energy, confirming active development status.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Maleza Storage project is a proposed 150.83 MW battery energy storage system in Wharton County, Texas. Developed by Brush Storage, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-21INR0456, with a queue entry date of October 31, 2019. The proposed commercial operation date is December 31, 2028, and its interconnection agreement status is currently in the Facility Study phase.

The project consists solely of battery storage, with a total capacity of 150.83 MW. The point of interconnection is the tap Blue Hillje 345 kv Ckt.#27. The Maleza Storage project has appeared in recent news coverage regarding energy storage developments in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wharton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Brush Storage, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap Blue – Hillje 345 kv Ckt.#27

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.