Chariot Storage
50 MW storage in Limestone, TX · In queue since March 2019 · Proposed COD February 2028
50 MW
Capacity
1
Components
Battery
7y 4m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-29
The Chariot Storage project is a proposed 50 MW battery storage development in Limestone County, Texas. The project, being developed by Chariot Storage LLC, is interconnected within the ERCOT region under queue ID ERCOT-21INR0260. It entered the queue on March 6, 2019, and has a proposed commercial operation date of February 29, 2028. Its interconnection status is currently in the Facility Study phase.
The project consists of 50 MW of battery storage capacity. The Chariot Storage project has been the subject of recent news coverage related to deals.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Limestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Chariot Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 69kV 99 Ben Hur - 107 Prairie Hill
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Ben Hur Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.