Indigo Solar
150 MW hybrid in Fisher, TX · In queue since September 2018 · Proposed COD September 2027
150 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Phase
Signed Sep 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 years
IA → COD
7 years
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-09-17
Projected COD moved
4 times
Dec 2021 → Sep 2027
Net change
+69 months
first report to latest
Capacity
125 → 150 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
- 2022-01·Innovative Solar Solutions→divestiture sought (buyer unknown)pv-magazine-usa.com
Milestones in this assessment
Innovative Solar Solutions sought buyer for IS245: Indigo Solar (125 MW) as part of 690 MW four-project portfolio
pv-magazine-usa.comResearch sources and reasoning (5 recorded sources)
low confidence at research time
- pv-magazine-usa.com/2022/01/04/acquisition-sought-for-four-texas-solar-projects-with-690-mw-combined-capacity/
- gem.wiki/Indigo_Solar
- interconnection.fyi/project/ercot-21inr0031
- renewablesinfo.org/plant/66891
- eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_05
Commercial operation date: LBNL proposes 2027-09-17 COD. No recent news or press releases provide an updated target date. EIA lists project as 'Planned for installation, but regulatory approval pending' with no operational timeline.
Developer: LBNL filing entity is 'Innovative Solar 245, LLC' (project shell). News from 2022 identifies parent as 'Innovative Solar Solutions' (ISS), which was seeking divestiture of four Texas projects including IS245: Indigo Solar.
Status: LBNL status is 'active' with IA executed in 2020. No evidence of construction start, withdrawal, or operational status. EIA confirms planned status with regulatory approval pending.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Indigo Solar is a proposed 150 MW solar generation project located in Fisher County, Texas. The developer is Innovative Solar 245, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-21INR0031, with a queue entry date of September 27, 2018, and a proposed commercial operation date of September 17, 2027.
The project's Interconnection Agreement (IA) was executed on September 15, 2022. Indigo Solar has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Innovative Solar 245, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26