Giddings Wind (ERCOT-21INR0006) — Project Summary

Queue ID
ERCOT-21INR0006
Capacity
240 MW
Technology
Wind
Status
active
Location
Upton, TX
Region
ERCOT
Developer
Pioneer Natural Resources
IA Status
Facility Study

Giddings Wind

ERCOT-21INR0006BetaActiveWindERCOTLBNL + Live

240 MW generation in Upton, TX · In queue since September 2017 · Proposed COD September 2030

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

240 MW

Capacity

1

Components

Wind

9y 2m

In Queue

Facility Study

IA Phase

COD target: 2030

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

13 years

Facilities Study50%
Queue EntrySep 6, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-09-09

Queue history
21INR0006 · 81 monthly ERCOT reports, Jan 2020 – Sep 2026

Projected COD moved

8 times

Oct 2021 → Sep 2030

Net change

+107 months

first report to latest

Capacity

240 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 6, 2017

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activityDelay announcedOilPrice.com · 2025-12-23
Delay reasonTrump administration stop-work orderOilPrice.com · 2025-12-23

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Sep 9, 2030
From queue filing
Developer in saved assessment
Pioneer Natural Resources
From queue filing
Status at research time
Active
Active — Facility Study stage per LBNL queue, no public announcements of construction timeline or financing
Financing
Not recorded
Research sources and reasoning (1 recorded sources)

low confidence at research time

  1. cleanview.co/planned-wind-projects/TX/21INR0006/giddings-wind

Commercial operation date: Only LBNL queue data provides a COD estimate (Sept 2030). No press releases, financing announcements, or developer updates found in search results to validate or contradict this date.

Developer: LBNL lists Pioneer Natural Resources as developer. No news coverage of this specific project found to confirm current ownership or reveal shell-LLC structure. Pioneer is an oil & gas company, not a typical renewable developer, which is unusual but not contradicted by available evidence.

Status: LBNL status is 'active' at Facility Study stage (early interconnection phase). No news coverage found regarding project development, permitting, or construction activity.

Project lifecycle
as of 2025-12-23
PhasesuspendedOilPrice.com · 2025-12-23
OperationalNoOilPrice.com · 2025-12-23
Technologyoffshore_windOilPrice.com · 2025-12-23
DeveloperEquinorOilPrice.com · 2025-12-23
DelayAnnouncedOilPrice.com · 2025-12-23
Permit decisionDeniedOilPrice.com · 2025-12-23

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Giddings Wind project is a proposed 240 MW wind generation facility in Upton County, Texas. Developed by Pioneer Natural Resources, the project is located within the ERCOT region and entered the interconnection queue as ERCOT-21INR0006 on September 6, 2017. The proposed commercial operation date is September 9, 2030, and the project's interconnection status is currently in the Facility Study phase.

The Giddings Wind project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Upton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Pioneer Natural Resources

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

71212 Upton 138kV

Data Source

LBNL + Live

DeveloperEquinorOilPrice.com · 2025-12-23
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Upton Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.