Giddings Wind
240 MW generation in Upton, TX · In queue since September 2017 · Proposed COD September 2030
240 MW
Capacity
1
Components
Wind
9y 2m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
13 years
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-09-09
Projected COD moved
8 times
Oct 2021 → Sep 2030
Net change
+107 months
first report to latest
Capacity
240 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Research sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: Only LBNL queue data provides a COD estimate (Sept 2030). No press releases, financing announcements, or developer updates found in search results to validate or contradict this date.
Developer: LBNL lists Pioneer Natural Resources as developer. No news coverage of this specific project found to confirm current ownership or reveal shell-LLC structure. Pioneer is an oil & gas company, not a typical renewable developer, which is unusual but not contradicted by available evidence.
Status: LBNL status is 'active' at Facility Study stage (early interconnection phase). No news coverage found regarding project development, permitting, or construction activity.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Giddings Wind project is a proposed 240 MW wind generation facility in Upton County, Texas. Developed by Pioneer Natural Resources, the project is located within the ERCOT region and entered the interconnection queue as ERCOT-21INR0006 on September 6, 2017. The proposed commercial operation date is September 9, 2030, and the project's interconnection status is currently in the Facility Study phase.
The Giddings Wind project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pioneer Natural Resources
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
71212 Upton 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Upton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesMax 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Giddings Wind
Data-driven briefing on Giddings Wind — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.