Tres Bahias Solar
195 MW generation in Calhoun, TX · In queue since March 2019 · Proposed COD August 2026
195 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Phase
Signed Aug 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 5m
IA → COD
6 years
Total Duration
1y 5m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2026-08-31
Projected COD moved
31 times
Dec 2020 → Aug 2026
Net change
+68 months
first report to latest
Capacity
195 MW
unchanged in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Project expected operational by end of 2023 per May 2023 announcement
houstonpublicmedia.orgProject brought online and generating energy, equipped with First Solar panels
huschblackwell.comResearch sources and reasoning (7 recorded sources)
high confidence at research time
- houstonpublicmedia.org/articles/news/energy-environment/2023/05/03/450717/renewable-energy-company-swift-current-building-195-megawatt-solar-farm-south-of-houston/
- prnewswire.com/news-releases/swift-current-energy-announces-power-purchase-agreement-and-tax-equity-financing-for-260-mw-solar-project-in-texas-302098858.html
- power-technology.com/news/swift-current-secures-financing/
- pv-tech.org/ideematec-to-supply-trackers-for-parliament-solar-project-in-texas/
- huschblackwell.com/inthenews/husch-blackwell-assists-swift-current-in-bringing-260-mw-solar-project-online-in-texas
- gem.wiki/Tres_Bahias_Solar
- swiftcurrentenergy.com/project/tres-bahias/
Commercial operation date: LBNL proposed COD was 2026-04-30, but multiple 2024 sources confirm the project is already operational. Husch Blackwell press release (Mar 2024) states the project is 'generating energy,' and Global Energy Monitor (Feb 2026) lists it as 'operating.' Swift Current's May 2023 announcement targeted end-of-2023 completion.
Developer: LBNL filing entity is 'Tres Bahias Solar Power LLC' (project-specific shell), but all news sources and Swift Current's own website confirm Swift Current Energy is the developer, owner, and operator of the project.
Status: Despite LBNL showing 'active' with is_operational=false, March 2024 press release confirms project is 'generating energy' and Feb 2026 Global Energy Monitor lists status as 'operating.'
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Tres Bahias Solar project is a proposed 195 MW solar generation facility located in Calhoun County, Texas. The developer is Tres Bahias Solar Power LLC. The project is listed in the ERCOT interconnection queue as entry ERCOT-20INR0266, with a queue entry date of March 26, 2019, and a proposed commercial operation date of February 28, 2026. The interconnection agreement (IA) has been executed as of August 7, 2020.
The proposed project is linked to the existing Tres Bahias operating plant (EIA plant ID 65947). The Tres Bahias Solar project has been the subject of recent news coverage, with 31 articles appearing in the press.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Calhoun
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tres Bahias Solar Power LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8140 Joslin 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TREB_SOLAR1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all 5 articlesTres Bahias Solar
Data-driven briefing on Tres Bahias Solar — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
What's the status of the 1 queue project linked to Tres Bahias?
Structured data lookup for Tres Bahias with rankings and aggregations.
Tres Bahias
Data-driven briefing on Tres Bahias — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.