Tres Bahias Solar is a 195 MW Solar project in Texas, currently active.
Tres Bahias Solar Power LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-30.
- Queue ID
- ERCOT-20INR0266
- Location
- Calhoun, Texas
- Technology
- Solar
- Developer
- Tres Bahias Solar Power LLC
- Market / region
- ERCOT
- Point of interconnection
- 8140 Joslin 138kV
What stands out
Tres Bahias Solar is a 195 MW Solar project in Texas with status active.
Tres Bahias Solar Power LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2026-04-30.
Latest linked story: “SWIFT CURRENT ENERGY ANNOUNCES POWER PURCHASE AGREEMENT AND TAX EQUITY FINANCING FOR 260 MW SOLAR PROJECT IN TEXAS” (PR Newswire, 2024-03-26).
Market and operating context
- Queue date
- 2019-03-26
- Proposed COD
- 2026-04-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.