Crowded Star Solar
218.79 MW hybrid in Jones, TX · In queue since January 2019 · Proposed COD August 2026
218.79 MW
Capacity
1
Components
Solar
7y 10m
In Queue
IA Executed
IA Phase
Signed Jul 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 6m
IA → COD
3y 1m
Total Duration
4y 6m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2026-08-17
Projected COD moved
13 times
Jul 2021 → Aug 2026
Net change
+61 months
first report to latest
Capacity
400 → 219 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Expected online date August 2026 per LBNL filing and third-party tracking
cleanview.coResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-20inr0241
- cleanview.co/power-projects/planned/solar-farms/texas/20INR0241/crowded-star-solar
- ercotqueue.com/developer/jones-city-solar-ii-llc
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
Commercial operation date: LBNL proposed COD of 2026-08-17 aligns with multiple third-party sources (Cleanview, ERCOT data) showing 2026 expected online date. No contradictory recent announcements found.
Developer: Only LBNL filing entity 'Jones City Solar, LLC' is available. No press releases or corporate announcements found identifying a parent operating company. The entity appears to be the actual developer rather than a shell LLC based on consistent usage across ERCOT filings and related Phase II project.
Status: LBNL status 'active' with IA executed 2023-07-27 is confirmed by ERCOT queue data showing 'IA + FIS complete' status. No withdrawal or construction announcements found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Crowded Star Solar project is a proposed 218.79 MW solar generation facility in Jones County, Texas. The project, developed by Jones City Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-20INR0241. It entered the interconnection queue on January 21, 2019, and has a proposed commercial operation date of July 8, 2026.
The project's Interconnection Agreement (IA) was executed on December 17, 2019. Recent news coverage indicates industry interest in the development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Jones City Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesCrowded Star Solar
Data-driven briefing on Crowded Star Solar — fleet, generation, financial, and news signals.
Star Solar
Data-driven briefing on Star Solar — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.