Norton Solar
128.48 MW generation in Runnels, TX · In queue since March 2017 · Proposed COD November 2025
128.48 MW
Capacity
1
Components
Solar
9y 8m
In Queue
IA Executed
IA Phase
Signed Jun 2019
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 3m
IA → COD
6y 5m
Total Duration
2y 3m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2025-11-24
Projected COD moved
8 times
Dec 2019 → Nov 2025
Net change
+71 months
first report to latest
Capacity
125 → 128 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- —·8minute Solar Energy→Avantussolarpowerworldonline.com
Milestones in this assessment
Project financing secured with MUFG as lender, Toyota Tsusho America as equity partner
power-technology.comCommercial operations achieved; construction completion announced March 18-19, 2026
powermag.comResearch sources and reasoning (8 recorded sources)
high confidence at research time
- electrek.co/2026/03/18/toyota-locks-in-power-from-a-massive-new-texas-solar-farm/
- solarpowerworldonline.com/2026/03/avantus-completes-159-mw-solar-project-in-central-texas/
- powermag.com/avantus-toyota-group-complete-construction-of-texas-solar-power-project/
- pv-tech.org/avantus-toyota-complete-construction-159mw-us-solar-project/
- renewablesnow.com/news/avantus-wraps-up-125-mw-texas-solar-project-for-toyota-tsusho-1291695/
- avantus.com/news/avantus-and-toyota-tsusho-america-begin-construction-of-norton-solar-project
- solarpowerworldonline.com/2024/08/avantus-breaks-ground-159-mw-texas-solar/
- power-technology.com/news/avantus-tai-norton-solar-project/
Commercial operation date: Multiple independent sources (POWER Magazine, Solar Power World, PV Tech, Renewables Now) confirm construction completion and commercial operations in March 2026. LBNL's 2025-11-24 target was approximately 4 months early but within typical project schedule variance.
Developer: LBNL filing entity 'TAI Norton Solar, LLC' is a project-specific LLC. All recent press releases and news coverage identify Avantus (formerly 8minute Solar Energy) as the developer and Toyota Tsusho America (TAI) as the financial partner/buyer, not the developer.
Status: LBNL shows 'Active' with IA Executed, but construction was completed and the project reached commercial operations in March 2026 according to coordinated announcements from Avantus, Toyota, and multiple trade publications.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Norton Solar project is a proposed 128.48 MW solar generation facility in Runnels County, Texas. Developed by TAI Norton Solar, LLC, the project consists of 128.48 MW of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-19INR0035, with a queue entry date of March 6, 2017, and a proposed commercial operation date of November 24, 2025. The project's Interconnection Agreement (IA) was executed on June 20, 2019.
The proposed project is linked to the existing Norton Solar Farm operating plant (EIA ID 61967). It has appeared in recent news coverage related to development and deals.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Runnels
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
TAI Norton Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60451 Garnet 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
- POI Substation
- Colorado River Municipal Water District #2 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-21