Norton Solar is a 128 MW Solar project in Texas, currently active.
TAI Norton Solar, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2025-11-24.
- Queue ID
- ERCOT-19INR0035
- Location
- Runnels, Texas
- Technology
- Solar
- Developer
- TAI Norton Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- 60451 Garnet 138kV
What stands out
1
Norton Solar is a 128 MW Solar project in Texas with status active.
2
TAI Norton Solar, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2025-11-24.
4
Latest linked story: “Avantus, Toyota Group Complete Construction of Texas Solar Power Project” (POWER Magazine, 2026-03-19).
Market and operating context
- Queue date
- 2017-03-06
- Proposed COD
- 2025-11-24
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters