San Bernard Solar (ERCOT-19INR0030) — Project Summary

Queue ID
ERCOT-19INR0030
Capacity
100 MW
Technology
Solar
Status
suspended
Location
Wharton, TX
Region
ERCOT
Developer
Sunchase Power
IA Status
Facility Study

San Bernard Solar

ERCOT-19INR0030BetaSuspendedSolarERCOTLBNL

100 MW generation in Wharton, TX · In queue since January 2017 · Proposed COD January 2022

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

100 MW

Capacity

1

Components

Solar

9y 10m

In Queue

Facility Study

IA Phase

COD target: 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5 years

Suspended50%
Queue EntryJan 25, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-01-01

Queue history
19INR0030 · 18 monthly ERCOT reports, Dec 2018 – May 2020

Projected COD moved

1 time

Jun 2020 → Jun 2021

Net change

+12 months

first report to latest

Capacity

100 MW

unchanged in the reports

Latest stage

Cancelled

last listed May 2020

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 26, 2017
CancelledSep 19, 2024
On ERCOT's inactive listJun 2020 – Aug 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneconstruction financing secured · 2025-05-13Construction Review · 2026-02-06
Project lifecycle
as of 2026-02-06
PhaseConstructionConstruction Review · 2026-02-06
OperationalNoConstruction Review · 2026-02-06
TechnologyHybridConstruction Review · 2026-02-06
DeveloperAypa Power, CDH Vidal LLCConstruction Review · 2026-02-06
PPA offtakerSan Diego Community PowerConstruction Review · 2026-02-06
Permit decisionGrantedConstruction Review · 2026-02-06

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

San Bernard Solar is a proposed 100 MW solar generation project located in Wharton County, Texas. The project, being developed by Sunchase Power, is interconnected within the ERCOT region under queue ID ERCOT-19INR0030. The project entered the ERCOT interconnection queue on January 26, 2017, and its interconnection status is currently in the Facility Study phase.

The proposed project consists of 100 MW of solar capacity. San Bernard Solar has been mentioned in recent news coverage related to the energy industry and grid development.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: May 2020.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wharton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Sunchase Power

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 138kV 43012 New Gulf - 43340 Texas Gulf Sulphur

Data Source

LBNL

DeveloperAypa Power±Construction Review · 2026-02-06
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.