Grandfalls Solar (ERCOT-19INR0002) — Project Summary

Queue ID
ERCOT-19INR0002
Capacity
175.6 MW
Technology
Solar+Battery
Status
active
Location
Upton, TX
Region
ERCOT
Developer
Nextera
IA Status
IA Executed

Grandfalls Solar

ERCOT-19INR0002BetaActiveSolarBatteryERCOTLBNL + Live

175.6 MW hybrid in Upton, TX · In queue since May 2016 · Proposed COD November 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

175.6 MW

Capacity

1

Components

Solar

10y 6m

In Queue

IA Executed

IA Phase

Signed Jan 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

8y 8m

IA → COD

1y 10m

Total Duration

8y 8m

Construction75%
Queue EntryMay 24, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 23, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-11-25

Queue history
19INR0002 · 71 monthly ERCOT reports, Dec 2018 – Sep 2026

Projected COD moved

6 times

May 2021 → Nov 2026

Net change

+66 months

first report to latest

Capacity

350 → 176 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 24, 2016
Facilities study approvedDec 17, 2025
Interconnection agreement signedJan 23, 2025
Approved for energizationJun 24, 2026
Approved for synchronizationJul 15, 2026
On ERCOT's inactive listApr 2020 – Feb 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jul 2027
Differs from queue: Nov 25, 2026From queue filing
Developer in saved assessment
NextEra Energy
Filed as King Mountain Solar, LLC
Status at research time
Active
Active — IA executed January 2025, construction targeting July 2027 COD per ERCOT capacity planning documents
Financing
Not recorded

Milestones in this assessment

IA executedJan 23, 2025

Interconnection Agreement executed with ERCOT

interconnection.fyi
COD targetJul 2027Latest in this assessment

Commercial operation date targeted for July 2027 per ERCOT MORA

ercot.com
Research sources and reasoning (6 recorded sources)

high confidence at research time

  1. interconnection.fyi/project/ercot-19inr0002
  2. comptroller.texas.gov/economy/docs/active-list.xlsx
  3. ercot.com/files/docs/2026/01/08/Capacity-Changes-by-Fuel-Type-Charts_December_2025.xlsx
  4. ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
  5. ercot.com/files/docs/2026/04/02/MORA_June2026.pdf
  6. ercotqueue.com/developer/king-mountain-solar-llc

Commercial operation date: LBNL proposed COD of July 2027 is corroborated by multiple independent ERCOT sources including the April 2026 MORA report and January 2026 capacity changes spreadsheet, both listing 2027 as the target year with no contradictory signals.

Developer: Texas Comptroller active agreements document reveals the project was 'in the past called Grandfalls Solar' but is now 'King Mountain Solar', which is the filing entity. LBNL lists 'Nextera' as developer, referring to NextEra Energy, the parent operating company.

Status: LBNL shows IA executed on 2025-01-23 with active status. ERCOT's June 2026 MORA and capacity tracking confirm the project remains on track for 2027 with no withdrawal or suspension signals.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Grandfalls Solar project is a proposed 178 MW solar generation facility in Upton County, Texas. The project, developed by Nextera, is located within the ERCOT region and interconnected to the ERCOT queue as entry ERCOT-19INR0002 on May 24, 2016.

The proposed commercial operation date for Grandfalls Solar is July 1, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 345kV 11028 Odessa - 76000 N McCamey. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Upton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Nextera

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

842 King Mountain Station 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.