Nazareth Solar
203 MW generation in Castro, TX · In queue since June 2014 · Proposed COD August 2027
203 MW
Capacity
1
Components
Solar
12y 5m
In Queue
IA Executed
IA Phase
Signed Jun 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
9 years
IA → COD
4y 2m
Total Duration
9 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-08-31
Projected COD moved
9 times
May 2020 → Aug 2027
Net change
+87 months
first report to latest
Capacity
201 → 203 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Project in pre-construction targeting 2026 commercial operation
gem.wikiResearch sources and reasoning (7 recorded sources)
high confidence at research time
- prnewswire.com/news-releases/vesper-energy-closes-236-million-financing-for-201-mw-nazareth-solar-302787087.html
- stocktitan.net/news/GCMG/vesper-energy-closes-236-million-financing-for-201-mw-nazareth-bu8byp9ipkwi.html
- renewablesnow.com/news/vesper-energy-closes-financing-for-201-mw-project-in-texas-1295713/
- citybiz.co/article/853490/vesper-energy-secures-236-million-for-texas-solar-project-as-ercot-demand-surges/
- tipranks.com/news/private-companies/vesper-energy-secures-236-million-to-build-201-mw-nazareth-solar-in-texas-ercot-market
- gem.wiki/TX_Nazareth_solar_farm
- newschannel10.com/2023/07/05/solar-power-farm-coming-nazareth-area-around-2025/
Commercial operation date: LBNL lists 2027-08-31, but Vesper Energy's financing close announcement (Jan 2025) and Global Energy Monitor's Feb 2026 reference suggest construction timeline targeting 2026. The 2023 news article mentioned 'around 2025' which has passed. Financing secured in Jan 2025 typically implies 12-18 month construction for solar.
Developer: LBNL filing entity is 'TX Nazareth Solar, LLC' (project shell). Multiple Jan 2025 press releases confirm Vesper Energy as the developer-operator closing $236M financing. The shell LLC is the legal interconnection applicant; Vesper Energy is the operating company.
Status: LBNL status is 'Active' with IA executed June 2023. Vesper Energy's financing close (Jan 2025) with $236M debt package confirms project is moving to construction phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Nazareth Solar is a proposed 204 MW solar generation project located in Castro County, Texas. The developer is TX Nazareth Solar, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-16INR0049, with an interconnection queue entry date of June 19, 2014. The proposed commercial operation date is August 5, 2027. The project's Interconnection Agreement (IA) was executed on June 7, 2023. The point of interconnection (POI) is at tap 345kV 23914 Tule Canyon - 23912 Ogallala C2.
The Nazareth Solar project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Castro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
TX Nazareth Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 23914 Tule Canyon - 23912 Ogallala C2
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Tule Canyon Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTX Nazareth Solar
Data-driven briefing on TX Nazareth Solar — fleet, generation, financial, and news signals.
Nazareth Solar
Data-driven briefing on Nazareth Solar — fleet, generation, financial, and news signals.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.