Cattleman Wind B
201.6 MW generation in Castro, TX · In queue since September 2013 · Proposed COD September 2021
201.6 MW
Capacity
1
Components
Wind
12y 10m
In Queue
Facility Study
IA Phase
COD target: 2021
Total Duration
8 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-09-01
The Cattleman Wind B project is a proposed 201.6 MW wind generation facility in Castro County, Texas. The project, developed by RWE Renewables Development, LLC, is located within the ERCOT region and interconnected to the tap 345kV 79501 Ogallala - 79502 Windmill point of interconnection.
The project entered the ERCOT interconnection queue as ERCOT-16INR0014b on October 1, 2013. Its interconnection status is currently listed as "suspended" and is in the Facility Study phase.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Castro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Renewables Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 79501 Ogallala - 79502 Windmill
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Ogallala Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Cattleman Wind BForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.