Query
Cattleman Wind B
Type
Entity Briefing
Entity
Cattleman Wind B
Generated
2026-10-19T12:27:03.222Z

Briefing on Cattleman Wind B

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
202 MW
Proposed capacity
suspended
Current status
Wind
Technology
ERCOT
Market / region
2021-09-01
Proposed COD
Facility Study
Queue phase
Briefing/projectsuspended

Cattleman Wind B is a 202 MW Wind project in Texas, currently suspended.

RWE Renewables Development, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2021-09-01.

Queue ID
ERCOT-16INR0014b
Location
Castro, Texas
Technology
Wind
Developer
RWE Renewables Development, LLC
Market / region
ERCOT
Point of interconnection
tap 345kV 79501 Ogallala - 79502 Windmill

What stands out

1

Cattleman Wind B is a 202 MW Wind project in Texas with status suspended.

2

RWE Renewables Development, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2021-09-01.

Market and operating context

Queue date
2013-09-30
Proposed COD
2021-09-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Cattleman Wind B — verified asset snapshot

FieldValue
Queue IDERCOT-16INR0014b
LocationCastro, Texas
TechnologyWind
DeveloperRWE Renewables Development, LLC
Market / regionERCOT
Point of interconnectiontap 345kV 79501 Ogallala - 79502 Windmill
Queue date2013-09-30
Proposed COD2021-09-01