Harald (BearKat Wind B) (ERCOT-15INR0064b) — Project Summary

Queue ID
ERCOT-15INR0064b
Capacity
162.1 MW
Technology
Wind
Status
active
Location
Glasscock, TX
Region
ERCOT
Developer
McCrae Wind Energy II, LLC
IA Status
IA Executed

Harald (BearKat Wind B)

ERCOT-15INR0064bBetaActiveWindERCOTLBNL + Live

162.1 MW generation in Glasscock, TX · In queue since November 2013 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

162.1 MW

Capacity

1

Components

Wind

13 years

In Queue

IA Executed

IA Phase

Signed May 2018

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4y 6m

IA → COD

8y 7m

Total Duration

4y 6m

Construction75%
Queue EntryNov 27, 2013

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 30, 2018

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-12-03

Queue history
15INR0064b · 94 monthly ERCOT reports, Dec 2018 – Sep 2026

Projected COD moved

52 times

Oct 2019 → Dec 2026

Net change

+86 months

first report to latest

Capacity

162 MW

unchanged in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 27, 2013
Facilities study approvedSep 27, 2017
Interconnection agreement signedMay 30, 2018
Approved for energizationFeb 10, 2020
Approved for synchronizationMay 12, 2020

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Feb 2026
Differs from queue: Dec 3, 2026
Developer in saved assessment
Copenhagen Infrastructure Partners (CIP)
Filed as McCrae Wind Energy II, LLC
Status at research time
Active
Active — IA executed May 2018, project remains in pre-construction with February 2026 target COD per state records
Financing
Not recorded

Milestones in this assessment

IA executedMay 30, 2018

Interconnection Agreement executed with ERCOT

opensource.gridstatus.io
COD targetFeb 2026Latest in this assessment

Expected commercial operation date per Texas PUC official generator table

ftp.puc.texas.gov
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. renewablesnow.com/news/cip-sells-interest-in-196-mw-bearkat-i-wind-farm-in-texas-668599/
  2. ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
  3. cleanview.co/planned-wind-projects/TX/15INR0064b/harald-bearkat-wind-b
  4. renewablesinfo.org/project/ercot-15inr0064b-harald-bearkat-wind-b
  5. opensource.gridstatus.io/en/stable/interconnection_queues.html

Commercial operation date: LBNL shows June 2026, but Texas PUC official generator table (gentable.xls) and Cleanview both cite February 2026 as the expected COD. The 4-month difference is minor but research sources are more recent.

Developer: LBNL filing entity is McCrae Wind Energy II, LLC (project SPV). Multiple research sources (renewablesinfo.org, CIP's 2019 sale of BearKat I interest) identify CIP as the actual developer/owner. McCrae is the legal filing entity.

Status: LBNL status is 'active' with IA executed in 2018. No evidence of construction start, withdrawal, or cancellation in any source. Texas PUC and ERCOT records confirm continued planning status.

Project lifecycle
as of 2019-09-11
PhaseOnlineRenewables Now · 2019-09-11
OperationalYesRenewables Now · 2019-09-11
TechnologyWindRenewables Now · 2019-09-11
DeveloperCopenhagen Infrastructure PartnersRenewables Now · 2019-09-11

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Harald (BearKat Wind B) project is a proposed 162.1 MW wind generation project located in Glasscock County, Texas. The developer is CIP. It is interconnected within the ERCOT region under queue ID ERCOT-15INR0064b, with an interconnection queue entry date of November 27, 2013. The proposed commercial operation date is April 30, 2026.

The project's interconnection agreement (IA) was executed on May 30, 2018. The point of interconnection is the 59903 Bearkat 345kV substation. The Harald (BearKat Wind B) project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Glasscock

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

McCrae Wind Energy II, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

59903 Bearkat 345kV

Data Source

LBNL + Live

TransactionDivestitureRenewables Now · 2019-09-11
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.