CLPT-CLPT G16
300 MW hybrid in Platte, WY · In queue since April 2022 · Proposed COD December 2025
300 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Phase
COD target: 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 8m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only the LBNL snapshot provides a COD (proposed_cod 2025-12-31). No news or live search findings were available to confirm or revise it, so it may be stale.
Developer: The LBNL filing entity is a NextEra Energy Resources interconnection-holding LLC, so the parent is clearly NextEra Energy Resources. This is inferred from the entity name alone, with no external source confirming it.
Status: LBNL lists the project as active with ia_status 'IA Executed' and is_operational false. No external sources contradict or enrich this.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed project identified by queue ID CLPT-CLPT G16 is a 300 MW hybrid energy development in Platte County, Wyoming, in the western United States. It is classified under the Solar+Battery technology category. Its technology details list solar, wind and battery storage, though the only component with a specified capacity is solar, at 300 MW. The developer is NextEra Energy Resources Interconnection Holdings, LLC, and the project is planned to interconnect at the Cheyenne – Windstar 230 kV line.
The project is in the interconnection queue administered by Black Hills Cheyenne Light Fuel and Power Transmission (CLPT), which it entered on April 1, 2022. It is active in the queue and has requested both Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS). An interconnection agreement has been executed. The proposed commercial operation date is December 31, 2025.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WY
County
Platte
Grid Region
Mountain West
Market
—
Developer
NextEra Energy Resources Interconnection Holdings, LLC
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Service Type
NRIS/ERIS
Point of Interconnection
Cheyenne - Windstar 230kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
A specific company (e.g., NextEra Energy, Duke Energy)
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra Energy
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra entity test
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra-Blackwell Wind, LLC
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.