LAKE ELSINORE ADVANCED PUMPED STORAGE PROJECT
500 MW storage in Riverside, CA · In queue since June 2005 · Proposed COD December 2028
500 MW
Capacity
1
Components
Other Storage
21y 1m
In Queue
IA Executed
IA Phase
Signed Aug 2012
Queue → IA
7y 2m
IA → COD
16y 4m
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-12-31
The Lake Elsinore Advanced Pumped Storage Project is a proposed 500 MW pumped storage development in Riverside County, California. The project is located within the CAISO region and is interconnected with San Diego Gas & Electric (SDGE). It entered the CAISO interconnection queue as queue ID CAISO-72 on June 21, 2005, with a proposed commercial operation date of December 31, 2028.
The project's Interconnection Agreement (IA) was executed on August 11, 2012. The point of interconnection (POI) is the proposed Lee Lake Substation at 500 kV. The Lake Elsinore Advanced Pumped Storage Project has been the subject of recent news coverage related to regulatory matters.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Proposed Lee Lake Substation 500 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SPCJCT_1_B1
- POI Substation
- Lee
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about LAKE ELSINORE ADVANCED PUMPED STORAGE PROJECTForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.