ALTA VISTA SUNTOWER GENERATING STATION
132 MW hybrid in Los Angeles, CA · In queue since January 2008 · Proposed COD December 2027
132 MW
Capacity
2
Components
Solar + Battery
18y 10m
In Queue
IA Executed
IA Phase
Signed May 2019
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
11y 4m
IA → COD
8y 7m
Total Duration
11y 4m
Study Phase
TC
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; TC
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-11
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/caiso-297
- newsletter.interconnection.fyi/p/interconnection-weekly-project-updates-205
- cleanview.co/power-projects/planned/solar-farms/california/297_steam_turbine/alta-vista-suntower-generating-station
- infrasure.ai/project/caiso-297-alta-vista-suntower-generating-station
Commercial operation date: The only COD signal is the CAISO queue date of 2027-12-11. The aggregators (interconnection.fyi, Cleanview, and the June 2025 newsletter noting the date moved from 2025-04-14 to 2027-12-10) all mirror the queue data. None is an independent developer or press-release source.
Developer: The LBNL developer field is null, and no search result names a developer, parent, or operating company. The aggregator pages show the developer field as blank or gated.
Status: LBNL and the aggregators (interconnection.fyi) agree the project is active in the queue. No evidence of withdrawal, suspension, or construction was found. One aggregator (interxdata) labels it a gas project, which conflicts with every other source and was disregarded.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Alta Vista Suntower Generating Station is a proposed 132 MW hybrid solar and battery project located in Los Angeles County, California. The development project consists of 66 MW of solar generation paired with 66 MW of battery storage. It is interconnected to the CAISO grid under queue ID CAISO-297, with an original queue entry date of January 18, 2008. The proposed commercial operation date is December 11, 2027.
The project's interconnection agreement (IA) has been executed as of June 30, 2011. The project is connected to the Neenach-Bailey 66kV line and is within the service territory of Southern California Edison (SCE).
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Neenach-Bailey 66kV line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Tower
Data-driven briefing on Tower — fleet, generation, financial, and news signals.
ATI
Data-driven briefing on ATI — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.