Whiskey Diggings (CAISO-2259) — Project Summary

Queue ID
CAISO-2259
Capacity
414.4 MW
Technology
Solar
Status
active
Location
Sutter, CA
Region
CAISO
Developer
—
IA Status
Not Started

Whiskey Diggings

CAISO-2259BetaActiveSolarCAISOLBNL

414.4 MW generation in Sutter, CA · In queue since April 2023 · Proposed COD December 2030

BA: CISOISO/RTO: CAISONERC: WECCRC: RCW

414.4 MW

Capacity

1

Components

Solar

3y 7m

In Queue

Not Started

IA Phase

COD target: 2030

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

7y 8m

Study Phase

Cluster 15

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-31

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 31, 2030
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active in the CAISO queue (CAISO-2259, Sutter County). IA not started, and no public sign of permitting, construction or financing.
Financing
Not recorded
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/caiso-54802
  2. app.nrgmap.com/queues/caiso-2259
  3. infrasure.ai/project/caiso-2259-whiskey-diggings
  4. interconnection.fyi/projects/market/CAISO

Commercial operation date: Only queue-derived data exists. LBNL lists a proposed COD of 2030-12-31, and the aggregator pages (interconnection.fyi, Infrasure) repeat the same CAISO data. No press release, news item or developer statement gives an independent date.

Developer: The LBNL developer field is null, and no search result names a developer, parent or operating company. The other results are about historic mining sites unrelated to the solar project.

Status: LBNL shows 'active', and the NRG Map and interconnection.fyi pages confirm the project is still active in the queue. No source shows withdrawal or progress beyond the queue study stage.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Whiskey Diggings (queue ID CAISO-2259) is a proposed solar generation project in Sutter County, California. It has a total planned capacity of 414.4 megawatts (MW), all from solar photovoltaic generation. The project is located within the service territory of Pacific Gas and Electric Company (PG&E) and would connect to the grid at the Rio Oso 230 kV point of interconnection. No developer is identified in the available queue data.

The project entered the California Independent System Operator (CAISO) interconnection queue on April 17, 2023, and is being evaluated as part of the Cluster 15 study phase. Its queue status is active, and it has requested Energy Resource Interconnection Service (ERIS). The proposed commercial operation date is December 31, 2030. Negotiation of an interconnection agreement has not yet started.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

CA

County

Sutter

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

PGAE

Entity

CAISO

Service Type

ERIS

Point of Interconnection

RIO OSO 230 kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
RIOOSO_1_N033
POI Substation
Rio Oso Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.