Zinfandel Storage Center
153.69 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD February 2030
153.69 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 10m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-02-15
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Entered CAISO Cluster 15 interconnection queue as 153.69 MW battery storage project
caiso.comResearch sources and reasoning (5 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/california/54841_storage/zinfandel-storage-center
- caiso.com/documents/cluster-15-interconnection-requests.xlsx
- cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/integrated-resource-plan-and-long-term-procurement-plan-irp-ltpp/2024-2026-irp-cycle-events-and-materials/assumptions-for-the-2025-2026-tpp/mappingcifrom_cluster15_apps_09-25-24.xlsx
- interconnection.fyi/projects/state/CA/san-joaquin-county
- infrasure.ai/project/caiso-2235-zinfandel-storage-center
Commercial operation date: Only LBNL queue data provides a specific COD of February 15, 2030. Third-party aggregators (Cleanview, InfraSure) echo this date but cite LBNL as source. No independent press releases or news articles found to validate or update this target.
Developer: LBNL snapshot lists developer as null. No press releases, corporate announcements, or news coverage found identifying the project sponsor or operating company. CAISO cluster spreadsheets do not include developer information for this queue position.
Status: LBNL reports 'active' status with IA 'Not Started'. No news or public filings found indicating construction, permitting, financing, or other development milestones beyond initial queue entry in April 2023.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Zinfandel Storage Center is a proposed battery energy storage project in San Joaquin County, California. The development project has a total capacity of 153.69 MW, consisting entirely of battery storage. It would interconnect to the Pacific Gas and Electric Company (PG&E) system at the Bellota–Riverbank point of interconnection. No developer has been publicly identified in the available queue data.
The project is listed as active in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2235. It entered the queue on April 17, 2023, and is being studied as part of CAISO's Cluster 15. The project has requested Network Resource Interconnection Service (NRIS). Its proposed commercial operation date is February 15, 2030, and work on its interconnection agreement has not yet started.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
BELLOTA-RIVERBANK
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.