Tioga Pass
103 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD January 2028
103 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Listed in CAISO Cluster 15 with IA status 'Not Started' as of queue snapshot
caiso.comResearch sources and reasoning (5 recorded sources)
low confidence at research time
- caiso.com/documents/cluster-15-interconnection-requests.xlsx
- cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/integrated-resource-plan-and-long-term-procurement-plan-irp-ltpp/2024-2026-irp-cycle-events-and-materials/assumptions-for-the-2025-2026-tpp/mappingcifrom_cluster15_apps_09-25-24.xlsx
- cleanview.co/planned-battery-projects/CA/54879_storage/tioga-pass
- infrasure.ai/project/caiso-2231-tioga-pass
- sonomacleanpower.org/uploads/documents/Appendix-A-Offer-Form.xlsx
Commercial operation date: Only LBNL queue data provides a COD target of January 2028. No news articles, press releases, or developer announcements found to validate or contradict this date.
Developer: LBNL snapshot lists developer as null. Search results yielded no press releases, corporate announcements, or news coverage identifying the project developer or owner.
Status: LBNL reports 'active' status with IA 'Not Started'. Sonoma Clean Power document references 'Interconnection Phase 2 study complete' for projects in this cohort, consistent with early-stage queue position.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Tioga Pass is a proposed battery energy storage development project located in San Joaquin County, California. The project has a total capacity of 103.0 MW, consisting entirely of a single battery storage component. It is planned to interconnect at the Lockeford 115 kV point of interconnection within the service territory of Pacific Gas and Electric Company (PG&E). No developer is identified in the available data.
The project is listed in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2231, with a queue entry date of April 17, 2023. Its status is active, and it is being evaluated as part of CAISO's Cluster 15 study phase. The project has requested Network Resource Interconnection Service (NRIS). As of the latest data, the interconnection agreement process has not yet started. The proposed commercial operation date is January 31, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
LOCKEFORD 115 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LOCKFORD_7_N001
- POI Substation
- Lockeford Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.