Argos Solar
352.017 MW generation in San Bernardino, CA · In queue since April 2023 · Proposed COD June 2030
352.017 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Not Started
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 2m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/solar-farms/california/54767_photovoltaic/argos-solar
- infrasure.ai/project/caiso-2219-argos-solar
- futuregrid.io/interconnections/argos-solar/
- interxdata.com/projects/argos-solar-caiso-2219/
Commercial operation date: Only queue-derived data exists. LBNL, Cleanview and Infrasure all list a June 2030 COD (Cleanview: "expected to come online in June 2030"), and they appear to copy the same filing. FutureGrid's serial date 46757 converts to about 2028-01-05, but it is another queue aggregator with inconsistent fields, not a developer or press signal, so it is not treated as independent.
Developer: The LBNL developer field is null and no search result names a developer. The argos.solar hit is an unrelated French PV advisory firm, and the other Argos hits are consumer products or research.
Status: LBNL lists the project as active with no IA, and aggregator pages (interxdata, Infrasure, FutureGrid) repeat the active status. No news indicates withdrawal, permitting, or construction.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Argos Solar is a proposed 352.02 MW solar photovoltaic generation project located in San Bernardino County, California. The development project is listed in the interconnection queue of the California Independent System Operator (CAISO) under queue ID CAISO-2219, within the service territory of Southern California Edison (SCE). The project would consist of a single solar component with a capacity of 352.02 MW. It is proposed to interconnect at the Calcite 230 kV point of interconnection and has requested Energy Resource Interconnection Service (ERIS).
The project entered the CAISO queue on April 17, 2023, and is being studied as part of Cluster 15. Its queue status is active, and it has a proposed commercial operation date of June 1, 2030. As of the latest available data, the interconnection agreement process for the project had not yet started.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
CALCITE 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.