DANDELION HYBRID SOLAR (CAISO-2145) — Project Summary

Queue ID
CAISO-2145
Capacity
334.2 MW
Technology
Solar+Battery
Status
active
Location
Nye, NV
Region
CAISO
Developer
IA Status
System Impact Study

DANDELION HYBRID SOLAR

CAISO-2145BetaActiveSolarBatteryCAISOLBNL + Live

334.2 MW hybrid in Nye, NV · In queue since April 2021 · Proposed COD December 2027

BA: NEVPISO/RTO: CAISONERC: WECCRC: SPPW

334.2 MW

Capacity

2

Components

Solar + Battery

5y 3m

In Queue

System Impact Study

IA Phase

COD target: 2027

Interconnection

Total Duration

6y 8m

Study Phase

C14

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-26

Cross-source intelligence
Beta
Low confidence·4 sources·as of 2026-06-01
Expected COD
Dec 2027
From queue filing
Developer
Status
Active
Active — System Impact Study phase, no construction or financing announcements
Financing
Unannounced
Key milestones
IA executedApr 2021Most recent

Queue position 2145 entered CAISO interconnection queue April 2021

source
About

The DANDELION HYBRID SOLAR project is a proposed 334.2 MW hybrid solar and battery energy storage development in Nye County, Nevada. The project consists of a 223.33 MW solar photovoltaic array coupled with a 110.87 MW battery energy storage system. It is located within the California Independent System Operator (CAISO) region and is interconnected to the Vista Substation at 230 kV.

The project, identified as queue ID CAISO-2145, entered the CAISO interconnection queue on April 15, 2021. Its proposed commercial operation date is December 26, 2027. As of the latest data, the project's interconnection status is in the System Impact Study phase. The identified utility for the project is GLW. The DANDELION HYBRID SOLAR project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NV

County

Nye

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

GLW

Entity

CAISO

Service Type

NRIS

Point of Interconnection

Vista Substation 230 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Technology
Solar223.33 MW · 67%
Battery110.87 MW · 33%
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
STELLING_1_N007
POI Substation
Monta Vista Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about DANDELION HYBRID SOLAR
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.