DANDELION HYBRID SOLAR
334.2 MW hybrid in Nye, NV · In queue since April 2021 · Proposed COD December 2027
Withdrawn from the CAISO queue in May 2026, according to CAISO's queue (Oct 2026).
334.2 MW
Capacity
2
Components
Solar + Battery
5y 7m
In Queue
System Impact Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 8m
Study Phase
C14
Interconnection request submitted to ISO/RTO
Proposed COD: 2027-12-26
Project withdrew from interconnection queue
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Queue position 2145 entered CAISO interconnection queue April 2021
caiso.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/nevada/2145_storage/dandelion-hybrid-solar
- interconnection.fyi/project/caiso-2145
- caiso.com/documents/publicqueuereport.xlsx
- eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
Commercial operation date: LBNL queue shows proposed COD of December 2027, confirmed by multiple aggregator sites (Cleanview, interconnection.fyi). No press releases or developer announcements found to validate or contradict this date.
Developer: No developer identified in LBNL filing. No press releases, corporate announcements, or ownership records found in search results. All sources are queue aggregators repeating LBNL data without developer attribution.
Status: LBNL shows 'active' status in System Impact Study phase. No evidence of progression beyond study phase, no construction activity, permits, or financing announcements found.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The DANDELION HYBRID SOLAR project is a proposed 334.2 MW hybrid solar and battery energy storage development in Nye County, Nevada. The project consists of a 223.33 MW solar photovoltaic array coupled with a 110.87 MW battery energy storage system. It is located within the California Independent System Operator (CAISO) region and is interconnected to the Vista Substation at 230 kV.
The project, identified as queue ID CAISO-2145, entered the CAISO interconnection queue on April 15, 2021. Its proposed commercial operation date is December 26, 2027. As of the latest data, the project's interconnection status is in the System Impact Study phase. The identified utility for the project is GLW. The DANDELION HYBRID SOLAR project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NV
County
Nye
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Vista Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- STELLING_1_N007
- POI Substation
- Monta Vista Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Nevada
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
DANDELION HYBRID SOLAR
Data-driven briefing on DANDELION HYBRID SOLAR — fleet, generation, financial, and news signals.