ROCK VALLEY ENERGY CENTER (CAISO-2144) — Project Summary

Queue ID
CAISO-2144
Capacity
1023.64 MW
Technology
Solar+Battery
Status
active
Location
Nye, NV
Region
CAISO
Developer
IA Status
IA Executed

ROCK VALLEY ENERGY CENTER

CAISO-2144BetaActiveSolarBatteryCAISOLBNL + Live

1,023.64 MW hybrid in Nye, NV · In queue since April 2021 · Proposed COD March 2029

BA: NEVPISO/RTO: CAISONERC: WECCRC: SPPW

1,023.64 MW

Capacity

2

Components

Solar + Battery

5y 3m

In Queue

IA Executed

IA Phase

Signed Dec 2024

Interconnection

Queue → IA

3y 8m

IA → COD

4y 3m

Total Duration

3y 8m

Study Phase

C14

Construction75%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementDec 27, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2029-03-15

Cross-source intelligence
Beta
Medium confidence·4 sources·as of 2026-06-01
Expected COD
2029
From queue filing
Developer
Status
Active
Active — IA executed Dec 2024, BLM permitting in progress, project moving forward per Feb 2026 Basin and Range Watch update
Financing
Unannounced
Key milestones
Permit approvedOct 2024

BLM published project fact sheet and preliminary plan of development for 1,600 MW AC solar + storage facility

source
IA executedDec 27, 2024Most recent

Interconnection Agreement executed with CAISO

source
About

The Rock Valley Energy Center is a proposed hybrid solar and battery project located in Nye County, Nevada. The development project has a total capacity of 1023.64 MW, consisting of 508.56 MW of solar generation and 515.08 MW of battery energy storage.

The project is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-2144, with an entry date of April 15, 2021. The proposed commercial operation date is March 15, 2029, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the Beatty Substation at 230 kV.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

NV

County

Nye

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

GLW

Entity

CAISO

Service Type

ERIS

Point of Interconnection

Beatty Substation 230 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Technology
Solar508.56 MW · 50%
Battery515.08 MW · 50%
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.