APACHE STORAGE
203.699 MW storage in Fresno, CA · In queue since April 2021 · Proposed COD May 2029
203.699 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Nov 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 7m
IA → COD
4y 6m
Total Duration
3y 7m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2029-05-21
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with CAISO
caiso.comResearch sources and reasoning (2 recorded sources)
low confidence at research time
- caiso.com/documents/publicqueuereport.xlsx
- cleanview.co/power-projects/planned/battery-storage-projects/california/1930_storage/apache-storage
Commercial operation date: LBNL queue shows proposed COD of 2029-05-21. No developer announcements, press releases, or news coverage found for this specific project. Cleanview aggregator confirms the same May 2029 date, but this appears to be derived from LBNL data rather than independent confirmation.
Developer: LBNL snapshot shows null developer. No press releases, corporate announcements, or news articles identify the project developer or owner. Search results returned unrelated Apache-named projects in New Mexico and Texas.
Status: LBNL shows 'active' status with IA executed on 2024-11-19, indicating the project has secured interconnection rights. However, no public announcements of construction start, financing, or developer identity have been found.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The APACHE STORAGE project is a proposed 203.7 MW battery storage project located in Fresno County, California. The project is interconnected to the PG&E utility and is listed in the CAISO interconnection queue as queue ID CAISO-1930, with an entry date of April 15, 2021. The proposed commercial operation date is May 21, 2029, and the interconnection agreement has been executed.
The APACHE STORAGE project has been the subject of recent news coverage, with at least nine articles published regarding the project. These articles cover topics such as deals, regulatory matters, and industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Sanger 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SANGER_1_N001
- POI Substation
- Sanger Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesAPACHE STORAGE in ISO New England growth signals — PPAs, construction, new projects
Data-driven briefing on APACHE STORAGE — fleet, generation, financial, and news signals.
APACHE STORAGE growth signals — PPAs, construction, new projects
Data-driven briefing on APACHE STORAGE — fleet, generation, financial, and news signals.
APACHE STORAGE
Data-driven briefing on APACHE STORAGE — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.