ALLIUM HYBRID
224.877 MW hybrid in San Benito, CA · In queue since April 2021 · Proposed COD December 2030
224.877 MW
Capacity
2
Components
Solar + Battery
5y 3m
In Queue
IA Executed
IA Phase
Signed Mar 2025
Queue → IA
3y 11m
IA → COD
5y 9m
Total Duration
3y 11m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2030-12-15
The ALLIUM HYBRID project is a proposed 224.88 MW hybrid solar and battery energy storage development in San Benito County, California. The project consists of a 112.49 MW solar array coupled with a 112.39 MW battery energy storage system. It is located within the CAISO region and interconnects to the PGAE utility grid at the Crazy Horse Canyon-Hollister 115 kV Line.
The project, identified as CAISO-1921 in the CAISO interconnection queue, entered the queue on April 15, 2021. Its proposed commercial operation date is December 15, 2030. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Benito
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Crazy Horse Canyon-Hollister 115 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about ALLIUM HYBRIDForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.