BAYLANDS BATTERY
250 MW storage in San Mateo, CA · In queue since April 2021 · Proposed COD March 2030
250 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Sep 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 5m
IA → COD
4y 6m
Total Duration
4y 5m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2030-03-24
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per CAISO queue records
caiso.comResearch sources and reasoning (3 recorded sources)
low confidence at research time
- caiso.com/documents/publicqueuereport.xlsx
- cleanview.co/power-projects/planned/battery-storage-projects/california/1900_storage/baylands-battery
- infrasure.ai/project/caiso-1900-baylands-battery
Commercial operation date: Only source available is LBNL queue data showing proposed COD of 2030-03-24. No news articles or press releases found to validate or contradict this date.
Developer: LBNL snapshot shows null developer field. No press releases, corporate announcements, or news coverage found identifying the project developer or owner.
Status: LBNL shows 'active' status with IA executed on 2025-09-24 (likely typo for 2024-09-24 given current date). No public announcements found regarding construction start or financing.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Baylands Battery project is a proposed 250 MW battery storage project located in San Mateo County, California. The project is interconnected to the CAISO grid under queue ID CAISO-1900, with Pacific Gas & Electric (PGAE) as the utility. The project entered the interconnection queue on April 15, 2021, and has a proposed commercial operation date of March 24, 2030. Its interconnection status is currently in the System Impact Study phase.
The Baylands Battery project is being tracked due to its appearance in recent industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Mateo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Martin 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DALYCTY_1_N005
- POI Substation
- Martin Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.