CALVADA SPRINGS SOLAR
500 MW hybrid in Inyo, CA · In queue since April 2020 · Proposed COD December 2027
500 MW
Capacity
2
Components
Solar + Battery
6y 7m
In Queue
IA Executed
IA Phase
Signed Jun 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
5y 2m
IA → COD
2y 6m
Total Duration
5y 2m
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C13
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/project/caiso-1798
- infrasure.ai/project/caiso-1798-calvada-springs-solar
- pressreader.com/usa/inyo-register/20241207/281560886372756
Commercial operation date: Only the LBNL queue date of 2027-12-31 exists. The aggregator sites (interconnection.fyi, infrasure) repeat the same queue data and are not independent. No developer press release or news article gives a financing-backed COD target.
Developer: The LBNL developer field is null and no search result names a developer or parent company. The Calvada Energy result concerns the unrelated California Valley Solar Ranch and was not used.
Status: LBNL shows status active with ia_status 'IA Executed' (IA date 2025-06-12), and the aggregator pages confirm the project is still active. No source reports a withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed CALVADA SPRINGS SOLAR project is a 500 MW hybrid solar and battery energy storage development in Inyo County, California. The project consists of 250 MW of solar photovoltaic generation paired with a 250 MW battery energy storage system. It is located within the California Independent System Operator (CAISO) region and is interconnected at the Trout Canyon Substation 230 kV.
The project, identified as CAISO-1798 in the CAISO interconnection queue, entered the queue on April 15, 2020, with a proposed commercial operation date of December 31, 2027. Its interconnection status is currently in the System Impact Study phase. The identified utility is GLW. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Inyo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.