DELAMAR ENERGY STORAGE
256.29 MW storage in Clark, NV · In queue since April 2020 · Proposed COD June 2027
256.29 MW
Capacity
1
Components
Battery
6y 3m
In Queue
IA Executed
IA Phase
Signed Oct 2022
Queue → IA
2y 6m
IA → COD
4y 8m
Total Duration
2y 6m
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-06-01
The Delamar Energy Storage project is a proposed 256.29 MW battery storage project located in Clark County, Nevada. The project is in the California Independent System Operator (CAISO) interconnection queue, identified as CAISO-1796, with a queue entry date of April 15, 2020. The proposed commercial operation date is June 1, 2027. The interconnection agreement (IA) for the project was executed on October 19, 2022. The point of interconnection is the Eldorado Substation 230kV, and the project has appeared in recent industry news.
The development project consists solely of battery storage, with a total capacity of 256.29 MW. The project's interconnection utility is Southern California Edison (SCE), and the interconnection entity is CAISO.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NV
County
Clark
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Eldorado Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MCCULLGH_5_N101
- POI Substation
- Eldorado Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about DELAMAR ENERGY STORAGEForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.