Briefing on DELAMAR ENERGY STORAGE

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
256 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2027-06-01
Proposed COD
C13
Queue phase
Briefing/projectactive

DELAMAR ENERGY STORAGE is a 256 MW Battery project in Nevada, currently active.

The reported queue phase is C13. Proposed COD is 2027-06-01.

Queue ID
CAISO-1796
Location
Clark, Nevada
Technology
Battery
Market / region
CAISO
Point of interconnection
Eldorado Substation 230kV

What stands out

1

DELAMAR ENERGY STORAGE is a 256 MW Battery project in Nevada with status active.

2

The reported queue phase is C13; proposed COD is 2027-06-01.

Market and operating context

Queue date
2020-04-15
Proposed COD
2027-06-01
IA status
IA Executed
Study phase
C13
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

DELAMAR ENERGY STORAGE — verified asset snapshot

FieldValue
Queue IDCAISO-1796
LocationClark, Nevada
TechnologyBattery
Market / regionCAISO
Point of interconnectionEldorado Substation 230kV
Queue date2020-04-15
Proposed COD2027-06-01
IA statusIA Executed