SANBORN HYBRID 4
100 MW hybrid in Kern, CA · In queue since April 2020 · Proposed COD October 2025
100 MW
Capacity
2
Components
Solar + Battery
6y 3m
In Queue
IA Executed
IA Phase
Signed Dec 2024
Queue → IA
4y 8m
IA → COD
10 months
Total Duration
4y 8m
Schedule
9 months past proposed COD
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-10-01
Terra-Gen closed $1 billion financing for phase 2, expanding Edwards Sanborn to 3291MWh battery capacity
sourceEdwards & Sanborn complex including SANBORN HYBRID 4 achieved full commercial operation as largest US solar-plus-storage project
sourceInterconnection Agreement executed per CAISO queue (likely administrative finalization post-COD)
sourceThe SANBORN HYBRID 4 project is a proposed 100 MW hybrid solar and battery energy storage project located in Kern County, California. The development project consists of 50 MW of solar photovoltaic generation and a 50 MW battery energy storage system. The project is interconnected to the CAISO grid at the Windhub Substation 230kV and is in the CAISO interconnection queue as queue ID CAISO-1790, with an entry date of April 15, 2020. The proposed commercial operation date is October 1, 2025, and the Interconnection Agreement has been executed.
The SANBORN HYBRID 4 project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Windhub Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ALTA6B2_7_N003
- POI Substation
- Windhub Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SANBORN HYBRID 4Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.