SANBORN HYBRID 4
100 MW hybrid in Kern, CA · In queue since April 2020 · Proposed COD October 2025
100 MW
Capacity
2
Components
Solar + Battery
6y 7m
In Queue
IA Executed
IA Phase
Signed Dec 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 8m
IA → COD
10 months
Total Duration
4y 8m
Schedule
14 months past proposed COD
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C13
Project under construction
Typical: 18–30 months
Proposed COD: 2025-10-01
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Terra-Gen closed $1 billion financing for phase 2, expanding Edwards Sanborn to 3291MWh battery capacity
energy-storage.newsEdwards & Sanborn complex including SANBORN HYBRID 4 achieved full commercial operation as largest US solar-plus-storage project
canarymedia.comInterconnection Agreement executed per CAISO queue (likely administrative finalization post-COD)
caiso.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- canarymedia.com/articles/solar/the-biggest-solar-plus-storage-project-in-the-us-just-came-online
- energy-storage.news/edwards-sanborn-california-solar-storage-project-world-largest-bess-battery-system-fully-online/
- energy-storage.news/terra-gen-closes-us1-billion-financing-for-second-phase-of-co-located-3-2gwh-battery-storage-in-california-edwards-sanborn/
- energy-storage.news/batteries-at-worlds-largest-solar-plus-storage-project-supplying-california-community-energy-group/
- caiso.com/documents/publicqueuereport.xlsx
Commercial operation date: LBNL proposed COD of 2025-10-01 appears to be a placeholder or stale estimate. Multiple credible sources (Canary Media, Energy-Storage.News) confirm the Edwards & Sanborn solar-plus-storage complex came fully online in January 2024. SANBORN HYBRID 4 is part of this multi-phase Terra-Gen project that achieved full commercial operation over a year before LBNL's proposed date.
Developer: LBNL snapshot has null developer field. Multiple independent sources (Energy-Storage.News Sept 2022, Nov 2021) explicitly name Terra-Gen as the developer and owner of the Edwards & Sanborn facility, which includes SANBORN HYBRID 4. Terra-Gen secured $1 billion financing for phase 2 in September 2022.
Status: LBNL shows 'active' with IA executed December 2024, but this contradicts multiple January 2024 news reports confirming the entire Edwards & Sanborn complex (including this phase) came fully online. The IA execution date of 2024-12-11 may be an administrative update post-COD.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SANBORN HYBRID 4 project is a proposed 100 MW hybrid solar and battery energy storage project located in Kern County, California. The development project consists of 50 MW of solar photovoltaic generation and a 50 MW battery energy storage system. The project is interconnected to the CAISO grid at the Windhub Substation 230kV and is in the CAISO interconnection queue as queue ID CAISO-1790, with an entry date of April 15, 2020. The proposed commercial operation date is October 1, 2025, and the Interconnection Agreement has been executed.
The SANBORN HYBRID 4 project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Windhub Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- PHSP15
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlescan you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
SANBORN HYBRID 4
Data-driven briefing on SANBORN HYBRID 4 — fleet, generation, financial, and news signals.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.