BONANZA PEAK SOLAR FARM (CAISO-1655) — Project Summary

Queue ID
CAISO-1655
Capacity
641 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
CAISO
Developer
IA Status
IA Executed

BONANZA PEAK SOLAR FARM

CAISO-1655BetaActiveSolarBatteryCAISOLBNL + Live

641 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD December 2027

BA: NEVPISO/RTO: CAISONERC: WECCRC: SPPW

641 MW

Capacity

2

Components

Solar + Battery

7y 3m

In Queue

IA Executed

IA Phase

Signed Jun 2022

Interconnection

Queue → IA

3y 2m

IA → COD

5y 6m

Total Duration

3y 2m

Study Phase

C12

Construction75%
Queue EntryApr 12, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementJun 8, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-12-31

Cross-source intelligence
Beta
Medium confidence·3 sources·as of 2026-06-01
Expected COD
2027-12-31
From queue filing
Developer
EDF Renewables
From queue filing
Status
Active
Active — IA executed June 2022, PPA signed with SCPPA in Feb 2024 for 300MWac portion of project
Financing
In progress
PPA signed with SCPPA for 300MWac portion in Feb 2024; full project financing status not publicly disclosed
Key milestones
IA executedJun 8, 2022

Interconnection Agreement executed with CAISO

source
Financing closeFeb 2024Most recent

EDF Renewables signed PPA with SCPPA for 300MWac portion of Bonanza solar-plus-storage project

source
About

The Bonanza Peak Solar Farm is a proposed 641 MW hybrid solar and battery project in Clark County, Nevada. The development project, located within the California Independent System Operator (CAISO) region, consists of a 441 MW solar array coupled with a 200 MW battery energy storage system. The project entered the CAISO interconnection queue as CAISO-1655 on April 12, 2019, with a proposed commercial operation date of December 31, 2027.

The project's interconnection agreement (IA) was executed on June 8, 2022. The point of interconnection is the Trout Canyon Substation at 230 kV. Recent news coverage indicates activity related to deals involving the Bonanza Peak Solar Farm.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

NV

County

Clark

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

GLW

Entity

CAISO

Service Type

NRIS

Point of Interconnection

Trout Canyon Substation 230 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Technology
Solar441 MW · 69%
Battery200 MW · 31%
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
CANYONP4_7_GN001
POI Substation
Canyon

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.