KEY STORAGE 1
309.3 MW storage in Fresno, CA · In queue since April 2018 · Proposed COD October 2026
309.3 MW
Capacity
1
Components
Battery
8y 7m
In Queue
IA Executed
IA Phase
Signed Nov 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 7m
IA → COD
4y 11m
Total Duration
3y 7m
Schedule
2 months past proposed COD
Study Phase
C11
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C11
Project under construction
Typical: 6–18 months
Proposed COD: 2026-10-01
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- fresnocountyca.gov/files/sharedassets/county/v/1/public-works-and-planning/development-services/planning-and-land-use/environmental-impact-reports/key-energy-storage/key_energy_storage_project_deir_sep_2023-print.pdf
- interconnection.fyi/projects/market/CAISO
- cleanview.co/power-projects/planned/battery-storage-projects/california/1479_storage/key-storage-1
Commercial operation date: Only the LBNL proposed COD of 2026-10-01 is usable. The Cleanview listing mentions an 'August...' online date, but the year is truncated, so it can't be used. No press release or financing-backed target was found for this project.
Developer: LBNL lists no developer. The news-extracted 'NextEra Energy Resources' comes from articles about the Elkhorn BESS and an Orange County Power Authority PPA, and neither names Key Storage 1 or Q1479. The Fresno County DEIR snippet also names no developer. Attributing the project to NextEra would be unsupported.
Status: interconnection.fyi still lists Q1479 as Active, which matches LBNL. The county environmental review shows permitting activity, but there is no evidence of construction or withdrawal.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
KEY STORAGE 1 is a proposed 309.3 MW battery storage project located in Fresno County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1479, with a queue entry date of April 16, 2018. The proposed commercial operation date is October 1, 2026. The project has an Interconnection Agreement (IA) listed as Executed.
The project is interconnected to the PG&E utility grid at the Gates 500 kV point of interconnection. Recent news coverage of the project includes 4 articles related to regulatory matters, 2 about deals, and 1 each about industry and grid topics.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Gates 500 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FIFTHS_7_N003
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-07-10
View all articlesBattery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
KEY STORAGE 1
Data-driven briefing on KEY STORAGE 1 — fleet, generation, financial, and news signals.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.