Briefing on KEY STORAGE 1

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
309 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2026-10-01
Proposed COD
C11
Queue phase
Briefing/projectactive

KEY STORAGE 1 is a 309 MW Battery project in California, currently active.

The reported queue phase is C11. Proposed COD is 2026-10-01.

Queue ID
CAISO-1479
Location
Fresno, California
Technology
Battery
Market / region
CAISO
Point of interconnection
Gates 500 kV

What stands out

1

KEY STORAGE 1 is a 309 MW Battery project in California with status active.

2

The reported queue phase is C11; proposed COD is 2026-10-01.

3

Latest linked story: “Utility-Scale Energy Storage Procurements in 2026: Contracting and Risk Allocation” (Morgan Lewis, 2026-03-13).

Market and operating context

Queue date
2018-04-16
Proposed COD
2026-10-01
IA status
IA Executed
Study phase
C11
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

KEY STORAGE 1 — verified asset snapshot

FieldValue
Queue IDCAISO-1479
LocationFresno, California
TechnologyBattery
Market / regionCAISO
Point of interconnectionGates 500 kV
Queue date2018-04-16
Proposed COD2026-10-01
IA statusIA Executed