HEARTLAND 1
228.31 MW hybrid in Fresno, CA · In queue since May 2017 · Proposed COD June 2028
228.31 MW
Capacity
2
Components
Solar + Battery
9y 6m
In Queue
IA Executed
IA Phase
Signed Dec 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
6y 7m
IA → COD
4y 6m
Total Duration
6y 7m
Study Phase
C10
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C10
Project under construction
Typical: 18–30 months
Proposed COD: 2028-06-30
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
CEQA application filed for Heartland Solar Project (~300 MW AC solar + 300 MW storage) in western Fresno County
ceqanet.lci.ca.govInterconnection Agreement executed with CAISO per LBNL queue record
Target COD per CAISO queue and confirmed by CleanView tracking of CAISO-1379
cleanview.coResearch sources and reasoning (8 recorded sources)
low confidence at research time
- canarymedia.com/articles/solar/biggest-us-solar-storage-project-california
- ceqanet.lci.ca.gov/2022100609/2
- cleanview.co/power-projects/planned/battery-storage-projects/california/1379_storage/heartland-1
- cleanview.co/power-projects/planned/solar-farms/california/1379_photovoltaic/heartland-1
- interconnection.fyi/project/caiso-1379
- infrasure.ai/project/caiso-1379-heartland-1
- governing.com/infrastructure/massive-solar-plan-aims-to-transform-californias-agricultural-heartland
- taiyangnews.info/markets/north-america-pv-news-snippets-hangzhou-firsts-steve-akey-at-re-in-california-more
Commercial operation date: LBNL queue specifies proposed COD of 2028-06-30; CleanView independently confirms 'Expected online 2028' for CAISO-1379, consistent with the LBNL date. The TaiyangNews 'cod_achieved' signal (Aug 2024) is discarded as almost certainly misattributed — the IA was not even executed until Dec 2023 and the project is not listed as operational.
Developer: LBNL lists no developer (null); news extraction from Canary Media (Jan 2026, confidence 0.7) attributes the broader Valley Clean Infrastructure Plan in western Fresno County — where HEARTLAND 1 sits — to Golden State Clean Energy (backed by Westlands Water District). Attribution to this specific 228 MW queue entry is plausible but indirect; no filing-level LLC name is on record.
Status: LBNL confirms IA Executed (2023-12-04) and active queue status; CEQAnet filing corroborates an in-progress environmental review for a Heartland Solar project at matching location and scale in Fresno County.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The HEARTLAND 1 project is a proposed solar generation project located in Fresno County, California, with a total capacity of 156.04 MW. The project is in the CAISO interconnection queue as entry CAISO-1379, with a queue entry date of May 1, 2017, and a proposed commercial operation date of June 30, 2028. The interconnecting utility is PG&E.
The project's interconnection agreement (IA) was executed on December 4, 2023. The point of interconnection (POI) is Tranquility 230 kV. Recent news coverage has discussed the project in the context of industry developments.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Tranquility 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlescan you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.