AGUA CALIENTE SOLAR 2
20 MW generation in Maricopa, AZ · In queue since March 2016 · Proposed COD December 2016
20 MW
Capacity
1
Components
Solar
10y 4m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2016
Total Duration
9 months
Schedule
117 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2016-12-01
The AGUA CALIENTE SOLAR 2 project is a proposed 20 MW solar generation project located in Maricopa County, Arizona. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1222, with a queue entry date of March 8, 2016. The proposed commercial operation date is December 1, 2016.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The project's point of interconnection (POI) is the Hoodoo Wash Switchyard 500 kV, and the interconnecting utility is San Diego Gas & Electric (SDGE). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Maricopa
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Hoodoo Wash Switchyard 500 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about AGUA CALIENTE SOLAR 2Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.