Project BPA-G0832 — Project Summary

Queue ID
BPA-G0832
Capacity
25 MW
Technology
Battery
Status
active
Location
Snohomish, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G0832

BPA-G0832BetaActiveBatteryBPALBNL

25 MW storage in Snohomish, WA · In queue since December 2022 · Proposed COD October 2025

BA: BPATNERC: WECCRC: RCW

25 MW

Capacity

1

Components

Battery

3y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection

Total Duration

2y 10m

Schedule

7 months past proposed COD

In Study38%
Queue EntryDec 22, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-31

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

BPA-G0832 is a proposed 25 MW battery storage project located in Snohomish County, Washington. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of December 22, 2022. The proposed commercial operation date is October 31, 2025. The interconnection agreement status is listed as "In Progress (unknown study)".

The development project consists solely of battery storage, with a total capacity of 25 MW. The point of interconnection is the Murray: Snohomish Co PUD 115 kV Feeder 1.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Snohomish

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

Murray: Snohomish Co PUD 115 kV Feeder 1

Data Source

LBNL

Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No Ask reports yet for this entity.

Ask about Project BPA-G0832
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.