BPA-G0732
400 MW hybrid in Benton, WA · In queue since March 2022 · Proposed COD April 2027
400 MW
Capacity
2
Components
Solar + Battery
4y 4m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
Total Duration
5y 1m
Study Phase
Transition Cluster
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
BPA-G0732 is a proposed 400 MW hybrid solar and battery project located in Benton County, Washington. The project, which consists of 200 MW of solar generation and 200 MW of battery energy storage, is in the Bonneville Power Administration (BPA) interconnection queue. The queue entry date is March 11, 2022, with a proposed commercial operation date of April 15, 2027.
The interconnection agreement (IA) status for BPA-G0732 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Wautoma 500 kV substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
NRIS/ERIS
Point of Interconnection
Wautoma 500 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project BPA-G0732Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.