Avista-CS24-01
0.999 MW generation in Adams, WA · In queue since March 2024 · Proposed COD November 2024
0.999 MW
Capacity
1
Components
Solar
2y 8m
In Queue
IA Executed
IA Phase
COD target: 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8 months
Schedule
25 months past proposed COD
Study Phase
2024
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-11-15
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Avista-CS24-01 is a proposed 1.0 MW solar generation project located in Adams County, Washington, in the western United States. The development project consists of a single solar component and is planned to interconnect with the system of Avista Utilities at the S. Othello 13kV point of interconnection. No developer name or project name is identified in the available queue data, so the project is referenced by its queue identifier.
The project is listed in Avista's interconnection queue rather than that of an ISO or RTO, and it entered the queue on March 26, 2024. It is currently in active status and associated with the 2024 study phase. It has requested Network Resource Interconnection Service (NRIS). An interconnection agreement has been executed for the project, and its proposed commercial operation date was November 15, 2024.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WA
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
NRIS
Point of Interconnection
S. Othello 13kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Washington Solar
Summary analysis with parallel narrative sections and visualizations.
IMPA Washington Solar Park
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
IMPA Washington Solar Park 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Washington
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.