Avista-41
0.25 MW generation in Lincoln, WA · In queue since April 2014 · Proposed COD September 2014
0.25 MW
Capacity
1
Components
Gas
12y 3m
In Queue
—
IA Status
COD target: 2014
Total Duration
5 months
Schedule
144 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2014-09-15
The Avista-41 proposed project is a 0.25 MW gas-fired generation project located in Lincoln County, Washington. The project is interconnected to Avista Utilities' distribution system near the intersection of Bourne and Doerschlag Road.
The project is listed as active in Avista's interconnection queue, with an entry date of April 10, 2014. The proposed commercial operation date (COD) is September 15, 2014.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WA
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
Other
Point of Interconnection
Avista’s distribution system near the intersection of Bourne and Doerschlag Road in Lincoln County Washington
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Avista-41Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.