Avista-100
100 MW hybrid in Benewah, ID · In queue since September 2019 · Proposed COD December 2021
100 MW
Capacity
1
Components
Solar
6y 10m
In Queue
—
IA Status
COD target: 2021
Total Duration
2y 3m
Schedule
55 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
Avista-100 is a proposed 100 MW hybrid solar and battery project located in Benewah County, Idaho. The project consists of 100 MW of solar generation capacity. It is listed in the Avista Utilities interconnection queue as of September 27, 2019, with a proposed commercial operation date of December 31, 2021. The point of interconnection is the Benewah 230 kV Station.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Benewah
Grid Region
Mountain West
Market
—
Developer
—
Utility
Avista Utilities
Entity
Avista
Service Type
NRIS/ERIS
Point of Interconnection
Benewah 230 kV Station
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Avista-100Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.