407.7 MW Natural Gas Fired Combustion Turbine (368 MW) + Petroleum Liquids (40 MW) operating in Surry, VA
407.7 MW
Nameplate Capacity
6
Generators
units
Hybrid (2)
Technology
Natural Gas Fired Combustion Turbine + Petroleum Liquids
1970
Operating Since
Coordinates
37.1575, -76.6911
County
Surry, VA
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Virginia Electric & Power Co | Virginia Electric and Power | — |
| Owner(s) | Virginia Electric & Power Co | Dominion Energy | — |
| Status | Operating | — | — |
Gravel Neck is a 407.7 MW hybrid power plant located in Surry County, Virginia. The plant, which began operating in 1970, is owned by Dominion Energy and operated by Virginia Electric & Power Co. It utilizes both natural gas and petroleum liquids as primary fuels, employing six generators with natural gas-fired combustion turbine technology. Gravel Neck is ranked as the 14th largest power plant in Virginia out of 20, and 544th nationally out of 945 plants.
The plant operates within the PJM Interconnection, LLC balancing authority and the SERC NERC region. In its latest year of reported generation, Gravel Neck produced 115,421 MWh of electricity, achieving a capacity factor of 3.2%. Financial data indicates an installed cost of $240.41 per kW, as reported to FERC.
Generated from EIA, GEM, and public data sources
ISO/RTO
PJM
Market
ISO/RTO Member
NERC Region
SERC — SERC Reliability Corporation
Balancing Authority
PJM Interconnection, LLC (PJM)
Grid Voltage
230.0 kV
Regulatory Status
RE — Regulated
Entity Type
Investor-Owned Utility
Sector
Electric Utility
Historic generation and capacity factor for this asset — the foundation for forward forecasts on the InfraSure platform.
2.0K MWh
Latest Month
115.4K MWh
Annual Generation
3.2%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
CO₂ Intensity
1575 lb/MWh
NOx
2 lb/MWh
SO₂
0.098 lb/MWh
CH₄
0.032 lb/MWh
N₂O
0.004 lb/MWh
Capacity Factor
2.5%
Annual Net Gen
89 GWh
CO₂eq
1577 lb/MWh
Subregion
SERC Virginia/Carolina
Internal combustion · VIRGINIA ELECTRIC AND POWER COMPANY · Data from 2015–2024
$255/kW
Installed Cost
$-7/kW
Annual CapEx
$13.1/MWh
Operating Cost
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Surry Substation · 500 kV
Substation Distance
0 km
Operator
Virginia Electric and Power Company
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
GRAVLNK 13 KV GT3
Pricing Hub
DOMINION HUB
Location Type
Generation Node
Node Source
Curated node match
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Gravel NeckForward forecasts, scenario decomposition, and risk-decision tooling for this asset.