Search plants, projects, owners, and states
26 MW Natural Gas operating in Oktibbeha, MS
26 MW
Nameplate Capacity
2
Generators
units
Natural Gas Fired Combustion Turbine
Technology
2005
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
33.4523, -88.8015
Reference point reported to EIA.
County
Oktibbeha, MS
Nearby Plants
The starting substation is nearby, but its connection to this plant is unconfirmed.
2 mapped line sections connect the two facilities over 2.408 km. At least one endpoint uses a nearby spatial match.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Reverse views of the same physical route are grouped in the route selector. All source records are retained.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Mississippi State University | — | — |
| Owner(s) | Mississippi State University | — | — |
| Status | Operating | — | — |
Summary generated Mar 22, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
The Mississippi State University power plant, located in Oktibbeha County, Mississippi, has a total capacity of 26 MW. The plant began operating in 2005 and is owned and operated by Mississippi State University. It utilizes two natural gas-fired combustion turbine generators.
The plant's balancing authority is the Tennessee Valley Authority (TVA), and it falls within the SERC NERC region. In terms of size, the Mississippi State University plant ranks 25th out of 30 power plants in Mississippi and 1263rd out of 1963 plants nationally.
Grid Region
Southeast
Market
SEEM Participant
NERC Region
SERC — SERC Reliability Corporation
Balancing Authority
Tennessee Valley Authority (TVA)
Grid Voltage
13.2 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Commercial
Sector
Commercial Non-CHP
Connection evidence
Mapped route candidate
No generation data available for this plant.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$965/kW
Est. Construction Cost
Total estimated cost: $25.1M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
This plant's balancing authority participates in the Southeast Energy Exchange Market (SEEM). SEEM is a bilateral exchange — no public nodal pricing.
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.