Search plants, projects, owners, and states
180 MW BESS planned in Brazoria, TX
180 MW
Nameplate Capacity
1
Generators
unit
Batteries
Technology
Planned: —
Planned Operation
Coordinates
29.1504, -95.6212
County
Brazoria, TX
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Nexus Renewables U.S. Inc. | — | — |
| Owner(s) | Nexus Renewables U.S. Inc. | — | — |
| Status | Planned | — | — |
Brazos River BESS LLC is a battery energy storage system located in Brazoria County, Texas. The plant has a total capacity of 180 MW and consists of a single generator. The primary fuel source is electricity (MWH), indicating that it charges from the grid. Nexus Renewables U.S. Inc. operates the facility.
The plant operates within the Electric Reliability Council of Texas (ERCOT) balancing authority, which is part of the Texas Reliability Entity (TRE) NERC region. Brazos River BESS LLC ranks as the 140th largest power plant in Texas out of 224, and 342nd nationally out of 514 plants.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
No generation data available for this plant.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2023
$1,361/kW
Est. Construction Cost
Total estimated cost: $245.0M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
West Columbia Local Substation · 138 kV
Substation Distance
2.871 km
Operator
Texas-New Mexico Power
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
CAST_ESS_RN
Pricing Hub
HB_HOUSTON
Alt. Hub / Zone
LZ_HOUSTON
Location Type
Resource Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Brazos River BESS LLCForward forecasts, scenario decomposition, and risk-decision tooling for this asset.