Brazos River BESS
180.36 MW storage in Brazoria, TX · In queue since October 2023 · Proposed COD October 2027
180.36 MW
Capacity
1
Components
Battery
3y 1m
In Queue
IA Executed
IA Phase
Signed May 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 7m
IA → COD
2y 5m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-10-30
Projected COD moved
2 times
Dec 2026 → Oct 2027
Net change
+10 months
first report to latest
Capacity
180 → 180 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement executed between Brazos River BESS LLC and Texas-New Mexico Power Company
interchange.puc.texas.govTarget commercial operation date per ERCOT capacity tracking (confirmed 2027)
ercot.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercot.com/files/docs/2025/07/09/Capacity-Changes-by-Fuel-Type-Charts_June_2025.xlsx
- lorenz-g.github.io/tesla-megapack-tracker/all-big-batteries.html
- cleanview.co/planned-battery-projects/TX/26INR0314/brazos-river-bess
- eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_05
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-10-30. ERCOT capacity chart (July 2025) confirms 2027 target. No contradictory news sources found; EIA lists 2028-11 but this appears to be a conservative estimate. LBNL date is most specific and recent.
Developer: LBNL filing entity is 'Brazos River BESS LLC' (project-specific shell). Multiple tracking sources (Tesla Megapack tracker, Cleanview) identify parent company as 'Nexus Renewables U.S. Inc.' This follows standard project-LLC structure.
Status: LBNL shows IA executed on 2025-05-24. Texas PUC filing confirms 'ERCOT Standard Generation Interconnection Agreement' dated May 23, 2025. No construction announcements found; project remains in planning stage.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Brazos River BESS is a proposed 180.36 MW battery storage project located in Brazoria County, Texas. Developed by Brazos River BESS LLC, the project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-26INR0314 on October 4, 2023. Its proposed commercial operation date is October 30, 2027, and its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Brazos River BESS LLC operating plant (EIA ID 68814).
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Brazos River BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 39530 West Colombia LOCAL TNP - 39560 ANGLETON TNP
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CAST_ESS_RN
- POI Substation
- West Columbia Local Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.