80 MW Wind operating in Crosby, TX
80 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2018
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
33.6992, -101.5247
Reference point reported to EIA.
County
Crosby, TX
Nearby Plants
The available map data does not yet establish a route from this plant to the grid.
No suitable mapped facility was found in the area searched. Missing map data does not mean the plant has no grid connection.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
Owner data does not fully agree across sources.
Sources can describe different roles or reporting dates. The source-specific values below are retained for comparison.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Lorenzo Wind, LLC | NextEra Energy | — |
| Owner(s) | Lorenzo Wind, LLC | NextEra Energy | — |
| Status | Operating | operating | — |
Summary generated Mar 22, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Lorenzo Wind is an 80 MW wind power plant located in Crosby County, Texas. The facility began operating in 2018 and consists of a single generator utilizing onshore wind turbine technology. The plant is owned by NextEra Energy and operated by Lorenzo Wind, LLC. The facility uses GE2.3-116 wind turbines manufactured by GE Wind, with a rotor diameter of 116 meters and a hub height of 80 meters. Lorenzo Wind is interconnected to the Southwest Power Pool (SPP) balancing authority and resides within the MRO NERC region.
In its most recent year of operation, Lorenzo Wind generated 337,663 MWh of electricity, achieving a capacity factor of 48.2%. The plant holds a rank of 212 out of 245 wind facilities in Texas, and 809 out of 1424 nationally. Financial data indicates a power purchase agreement (PPA) price of $23.88 per MWh, as reported to FERC.
ISO/RTO
SPP
Market
ISO/RTO Member
NERC Region
MRO — Midwest Reliability Organization
Balancing Authority
Southwest Power Pool (SWPP)
Grid Voltage
115.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Connection evidence
Connection unresolved
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
35.7K MWh
Latest Month
337.7K MWh
Annual Generation
48.2%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
Historic financial signal for this asset — PPA, LCOE, market value where reported. The base for forward bankability and insurance analytics on the InfraSure platform.
Lorenzo Wind, LLC · Data from 2019–2025
$23.9/MWh
PPA Price
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
SPP
LMP Node
SPS.BONITA.LORENZO.WND
Pricing Hub
SPPSOUTH_HUB
Node Source
Curated node match
1 buyer • 28 active contracts
Last updated 2026-05-31
View all articlesA specific company (e.g., NextEra Energy, Duke Energy)
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra Energy
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra entity test
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
GSPP Held LLC CSG
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this asset.