Canceled or postponed, according to EIA. Last listed as operating or planned in August 2025. EIA-860M · Sep 2026
150 MW Wind in Crosby, TX
150 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
—
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
33.7137, -101.4338
Reference point reported to EIA.
County
Crosby, TX
Nearby Plants
The available map data does not yet establish a route from this plant to the grid.
No suitable mapped facility was found in the area searched. Missing map data does not mean the plant has no grid connection.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Tri Global Energy, LLC | Tri Global Energy | — |
| Owner(s) | Tri Global Energy, LLC | Tri Global Energy LLC | — |
| Status | Canceled or postponed | announced | — |
Summary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Crosby County Wind Farm, LLC, is a 150 MW wind power plant located in Crosby County, Texas. The facility, identified by plant ID 60273, utilizes onshore wind turbine technology and is operated by Tri Global Energy, LLC. It consists of a single generator powered by wind (WND) as its primary fuel source. The plant operates within the Electric Reliability Council of Texas, Inc. (ERCOT) balancing authority and the TRE NERC region.
The Crosby County Wind Farm is ranked as the 162nd largest power plant in Texas out of 200 facilities and holds a national ranking of 490 out of 734 plants. The plant has been the subject of 3 news articles, with coverage focusing on industry trends and grid-related topics.
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
—
Regulatory Status
NR — Non-Regulated
Entity Type
Commercial
Sector
IPP Non-CHP
Connection evidence
Connection unresolved
No generation data available for this plant.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2023
$1,468/kW
Est. Construction Cost
Total estimated cost: $220.2M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
ERCOT
LMP Node
—
Pricing Hub
HB_WEST
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Crosby County Wind Farm, LLCForward forecasts, scenario decomposition, and risk-decision tooling for this asset.